Vintage TBM Cuts Months Off Schedule in San Antonio - NAT2022
By Cody Edwards, Ross Webb
5 miles of soft ground tunnel excavation for the SAWS W‑6 project finished months early despite difficult conditions. Success was achieved using TBMs and other equipment built long before most of the
Dec 1, 2022
-
Underwater Tunnel Repair with Stainless Steel Segmental Liner - NAT2022
By Matthew Goff, Russell Lutch
The Great Lakes Water Authority (GLWA) operates the largest regional water authority in the State of Michigan. Two of the tunnels supplying raw water to the system from the Detroit River are the Sprin
Dec 1, 2022
-
Parametric Study of Portal Area Condition for Mountain Tunnel Damaged by Earthquake - NAT2022
By Hajime Kitamura, Nobuharu Isago, Yuta Yamanishi, Kosuke Kawata, Hiroshi Yagi, Akira Matsuoka
Mountain tunnels are generally considered to be stable during earthquakes, however, it is known that the portal areas are prone to seismic damages. Characteristics in portals such as the location of t
Dec 1, 2022
-
Lateral Deflections and Vertical Control in Tunnel Control Networks - NAT2022
By Joern Katzer
It is vitally important to any tunnel project to have an accurate and reliable survey control network inside the tunnel for layouts, as-built surveys, and to provide guidance to the tunnel boring mach
Dec 1, 2022
-
Transitioning from Mixed-Face Conditions to Hard Rock During TBM Launch on the Reedy River Basin Sewer Tunnel Project— Greenville, SC - RETC2021
By Horry Parker Jr, Jason Gillespie, Justin Kolster, Stephen O’Connell
Construction of the 5,932-ft Reedy River Basin Sewer Tunnel in Greenville, SC was marked by a critical transition from drill-and-blast mining in mixed-face conditions to TBM excavation with limited ro
Jun 13, 2021
-
Risk Modelling Techniques for Complex Tunnelling Projects from Deterministic to Probabilistic Methods: Have We Done Enough? - NAT2022
By P. Sander, M. Spiegl, J. Reilly, A. Van Droogenbroeck
Although the outdated idea of calculating risk as the deterministic product of its likelihood and impact is not entirely a thing of the past, a multitude of organizations have adopted the usage of pro
Dec 1, 2022
-
Dustless Hard Rock Tunneling Methods - RETC2021
By Cody Giroux, Homer Scurlock, Michel Wasag
Silica and Crystalline Quartz exposure continues to be a serious health threat to nearly 2 million workers in the United States, including more than 100,000 working in high risk jobs such as abrasive
Jun 13, 2021
-
A Case Study Establishing Optimization Techniques and the Procedure for Successful Numerical Simulation of Ground-Structure Interaction - NAT2022
By Ali Keneti, Xavier Ryan, Gerardo Sanchez, Shannon Goff
In this study, FLAC3D modeling was conducted for ground-structure stability assessment for a pilot tunnel passing under a large shaft excavated in the vicinity of existing structures at Karangahape St
Dec 1, 2022
-
Two-Component Backfill Grouting at the Three Rivers Protection and Overflow Reduction Tunnel: Above and Below Ground Challenges and Solutions - RETC2021
By Francesco Chiappalone, Tanner Murt, Lance Waddell, Cristina Oñate Salazar
The 3RPORT project is a 5-mile-long, 16-foot-internal-diameter tunnel excavated in hard rock by Slurry TBM in Fort Wayne, Indiana. Two-component grouting can be separated into two core areas of operat
Jun 13, 2021
-
Review of Measured Activity Times and Their Impacts on Machine Utilization in Operation of Selected TBMs - RETC2021
By P. Nelson, R. O’Connell, J. Rostami
Tunnel boring machine (TBM) system utilization is a critical factor for predicting machine performance. The process of estimating machine performance, including rate of penetration (ROP) and machine u
Jun 13, 2021
-
Three Rivers Protection and Overflow Reduction Tunnel (3RPORT) City of Fort Wayne Tunnel Alignment and Adit Redesign in Construction: A Schedule Driven Journey - NAT2022
By Todd S. Webster, Matthew J. Pierce, Brad D. Krumel
With the Working Shafts and Starter Tunnel under way, it became apparent this 4.7-mile, 19-foot diameter wet weather tunnel was going to live up to its name. The shaft’s pre-excavation grouting was co
Dec 1, 2022
-
The Use of Cloud-Based Geotechnical Software During the Final Design of the New Haven Downtown Storm Sewer Infrastructure Improvement Project - NAT2022
By Michael Schultz, Gregory Sanders
The City of New Haven is planning to construct the Downtown Storm Sewer Infrastructure Improvement project to mitigate on-going stormwater flooding in the Long Wharf District. The proposed project inc
Dec 1, 2022
-
Design and Construction of a Deep Underground Station in Urban Area - RETC2021
By Verya Nasri
This paper will present the design and construction of a deep underground station of the Réseau Express Métropolitain (REM) project; the Édouard Montpetit station. The Édouard-Monpetit station is an i
Jun 13, 2021
-
Methodologies for Sound Transit’s Proposed New Tunnels for LINK Light Rail Expansion - RETC2021
By Matthew Preedy, Anthony Pooley, Mike Wongkaew, Dirk Bakker, Raghu Bhargava
Sound Transit’s ST3 program will add 62 miles of light rail to the Puget Sound area, including connections to the neighborhoods of West Seattle currently anticipated by 2031 and Ballard by 2036. These
Jun 13, 2021
-
Design and Construction of the New Stormwater Storage and Drainage Tunnel System in the Michigan I‑75 Modernization Segment 3 P3 DBFM Contract - RETC2021
By David Mast, Amanda Foote, Mina Shinouda
The Michigan DOT’s I‑75 Modernization Project, Segment 3, is a 30-year, $1.2 Billion design-build-finance-maintain project in Southeast Michigan. The scope includes building a nearly 4-mile long, 14.5
Jun 13, 2021
-
Respirable Crystalline Silica Dust—Practical Impacts and Solutions in Tunnelling - RETC2021
By Rainer Antretter
While respirable crystalline silica (RCS) dust that arises in industrial production mostly emanates from point sources and can be well mitigated, the extraction of dust is much more difficult in under
Jun 13, 2021
-
High-Frequency InSAR Displacement Monitoring and Trend Detection Analysis for Tunneling Projects - RETC2021
By Marie-Josée Banwell, Cyriac Sebastian, Giacomo Falorni, Sara Del Conte
Interferometric Synthetic Aperture Radar (InSAR) is a satellite-based monitoring technique that complements other in-situ methods for detecting and measuring surface displacement. Recent advances in d
Jun 13, 2021
-
Improved Contracting Practices and Ground Risk Management Using Geostatistics - NAT2022
By Jacob Grasmick, Bill Newns
Despite ongoing digitization and “hardware” technological advances, geotechnical uncertainty remains the most significant risk in underground and tunnel construction. And, whilst they are commonly hel
Dec 1, 2022
-
Upgrading the Coal Creek Trunk Sewer - RETC2021
By Joseph Clare
It’s not the 1960s anymore. Upgrading wastewater pipelines in the current era demands the latest trenchless technology to minimize impacts. King County Wastewater Treatment Division in Seattle, Washin
Jun 13, 2021
-
Automatic Computation of TBM Face Pressure Using 3D Ground Model - RETC2021
By CK Tsang, Jack Muir, Dharman Gersch, Joshua Barry
Correct face pressure is critical to safe operation of a closed face TBM. If inadequate face pressure is applied, this will lead to excessive ground movement, and may result in collapse of the tunnel
Jun 13, 2021