New XRF Analyzer For Elemental Analysis Of Sample Streams
By C. Bachmann, M. J. Laurila, A. J. Widenman, A. Klein
Elemental analysis of slurry streams using X-ray fluorescence (XRF) has long been employed. However, detector technology has limited the application of XRF devices. Using detector technology employed
Jan 1, 1999
-
The Kensico-City Tunnel Will Add Reliability to New York City’s Water Supply System
By Verya Nasri, Heather M. Ivory, Kevin Clarke, Eric Cole
Development of the New York City Water Supply System The New York City water supply system serves a population of almost nine million, including residents in neighboring counties. Peak day demands
Jan 1, 2007
-
Handling The Impacts Of Blasting On Grand Central Terminal For The MTA?s East Side Access Project
By A. J. Thompson
The Metropolitan Transportation Authority (MTA) East Side Access project (ESA) will, when it is complete, provide a new link to the east side of Manhattan from Long Island, NY that, linked with the Se
Jan 1, 2012
-
Singapore’s Deep Tunnel Sewerage System—Experiences and Challenges
By Richard F. Flanagan, Robert H. Marshall
The Republic of Singapore’s Public Utilities Board is implementing the Deep Tunnel Sewerage System Project. The project’s deep tunnel component, 48 km of deep, large diameter sewer tunnels has been su
Jan 1, 2007
-
Limestone Mining – Is It Noisy Or Not? (a6f0b5ad-a610-4972-afd6-68c53ccd734c)
By D. R. Babich, E. R. Bauer
National Institute for Occupational Safety and Health (NIOSH) researchers are conducting a cross-sectional survey of equipment noise and worker noise exposures in the mining industry. Surface and und
Jan 1, 2006
-
DCF/NPV Modelling: Valuation Practice Or Financial Engineering?
By M. J. Lawrence
Independent natural resource Valuers are an essential link between miners and mineral explorers on the one hand and the finance industry on the other. Investors (and regulators) expect the mining and
Jan 1, 2000
-
Performance And Experiential Development Of The Mobile Miner At Mount Isa
By R. J. Boyd
SUMMARY The productivity of drill and blast methods of mining in hard rock is limited by the cyclic nature of the operation, and a plateau of performance has been reached, even with the most advanc
Jan 1, 1987
-
A 4.75m Contractor Manufactured EPB Machine
By Bruce Richardson
A contractor-manufactured 4.75m (15'-7") diameter EPB shield excavated a 115m (375 ft) long tunnel under the San Antonio River as part of the Salado Creek to Dos Rios Pipeline Interconnect Projec
Jan 1, 2008
-
Heavy mineral mining in the Atlantic Coastal Plain of Florida and Georgia and the chemical and physical characteristics of the deposits
By F. L. Pirkle, D. L. Pirkle, E. C. Pirkle, W. A. Pirkle
Heavy minerals have been mined from the sands of the United States’ Atlantic Coastal Plain since the early part of the twentieth century. Production of ilmenite from beach sands near Mineral City (Po
Jan 1, 2005
-
Weathering In Coal Mine Rejects And Tailings - Variation With Respect To Depth
By S. Devasahayam
Acid production or acid drainage is a major environmental issue that also has negative implications on the aquifer system surrounding the mine tailings area. The approach to controlling acid mine drai
Jan 1, 2007
-
Design-Build of the Lake Hodges to Olivenhain Pipeline Tunnel and Shaft
By Jon Y. Kaneshiro, Sean A. Menge, M. Luis Piek, Brian Barker
The Lake Hodges to Olivenhain Pipeline project is part of a 40-megawatt pumped storage project linking two reservoirs as part of the San Diego County Water Authority’s $939 million Emergency Storage P
Jan 1, 2007
-
Characterization Of Coal And Quartz Dust In Interior Basin Coal Mines
By Y. Paul Chugh
NIOSH and the Illinois Clean Coal Institute are funding studies on characterization of coal and quartz dust in Interior Basin mines since 2009. Coal dust characteristics vary significantly and, are vi
Jan 1, 2011
-
Practical Optimization Strategies for Coal-Washing Plants – Preprint 97-70
By R. P. King
The MODSIM mineral processing plant simultor is used to find optimal combinations of target separation specific gravities in a typical modem coal washing plant. A plant that is set up with these optim
Feb 24, 1997
-
Estimation Of Incremental Haulage Costs By Mining Historical Data And Their Influence In The Final Pit Limit Definition
By R. Benito
This paper describes the application of modern data-analysis tools, such as data mining, to determine a representative cost driver for haulage activity. This cost driver was subsequently used to trace
Jan 1, 2008
-
The Treatment Of Refractory Gold Ores Containing Carbonaceous Material And Sulfides
By W. J. Guay
Carbonaceous gold ores containing gold dispersed in sulfides are refractory to cyanidation because: (1 ) the carbonaceous materials adsorb gold during cyanidation; (2) a portion of the gold s so finel
Jan 1, 1981
-
The Optimum Production Equipment Scale For Open Pit Coal Mining
The trend for using larger equipment in open pit mining to achieve cost effectiveness raises the question about the optimum economic point of scale in the current world of globalization. The present p
Jan 1, 2004
-
Experimental Studies on Controlling Drilling Parameters to Reduce Roof Bolt-Hole Drilling Noise (e8dcc61b-ac47-48a5-a23e-35012db274c6)
By Yi Luo
Bolting the mine roof is one of the noisiest underground mining operations. The main contribution to the noise is the drilling of the roof bolt holes, especially drilling in hard rock. Previous resear
-
An Evaluation Of Engineered Cover Systems For Mine Waste Rock And Tailings
By M. E. Smith
Waste rock dumps, tailings impoundments and spent leach heaps are common features at mine sites. Many of these waste disposal facilities contain sulfide-rich minerals, which generate acid mine drainag
Feb 27, 2013
-
Characteristics Of Chimney Subsidence Sinkhole Development From Abandoned Underground Coal Mines Along The Colorado Front Range
By Gordon M. Matheson
The factors which control chimney subsidence sinkhole development in weak rock were assessed by analyzing the characteristics of approximately 3000 chimney subsidence features along the Colorado Front
Jan 1, 1986
-
Moving Forward on New York’s Second Avenue Subway
By David Caiden, Geoffrey Fosbrook, Jaidev Sankar, Donald Phillips, Jon Hurt, Anil Parikh
This paper will cover the progress being made on Phase 1 of New York’s Second Avenue Subway line. It will include a description of construction progress on the first contract to be let, which consists
Jan 1, 2007