Evaluation Of Movement Data And Ground Conditions For The Åknes Rock Slide
By V Kveldsvik, N Ragvin, T Eiken, G Grøneng, G V. Ganerød
Catastrophic rock slope failures have caused destructive tsunamis in Norwegian fjords. At the Åknes rock slope the tsunami generating potential is large due to the potential large volume involved in a
Jan 1, 2006
-
PNEUFLOT® - Modern Flotation Technology In The 21st Century
By Lutz Markworth, Wolfram Jaspers, Johannes Kottmann
PNEUFLOT® technology has been applied for the past 20 years in coal, ore and other minerals processing plants. During the last two years this technology has achieved a breakthrough with some 42 units
Jan 1, 2007
-
The Strategic And Tactical Value Of A 3D Geotechnical Model For Mining Optimization, Anglo Platinum, Sandsloot Open Pit
Sandsloot open pit is situated on the northern limb of the Bushveld Complex, 250 km north east of Johannesburg, South Africa. Sandsloot is currently the largest open pit platinum mine in the world and
Jan 1, 2006
-
Assessment Of The Risk Of Plug Or Water Barrier Failure Due To Seismicity At South Deep Mine
As part of a comprehensive risk analysis which was carried out into the effectiveness of the water barrier between South Deep and Randfontein Estate mines, the potential threat posed by large seismic
Jan 1, 2006
-
The development and implementation of industrial hydrometallurgical gallium and germanium recovery - Synopsis
The Gordonsville Operation of Pasminco US Inc. along with the Center for Advanced Mineral and Metallurgical Processing (CAMP) at Montana Tech studied, developed and implemented a pilot-scale hydrometa
Jan 1, 2008
-
Occupational Health And Safety Risks Associated With Sulphur Dioxide
By C. J. Badenhorst
Oxides of sulphur are corrosive and are produced when sulphur-containing fuels are burned. Sulphur dioxide (SO2) is a colourless gas with a characteristic, irritating, pungent odour. Exposure routes t
Jan 1, 2007
-
Copper Mining in Zambia – History and Future
By Cade Mweemba, Alex Mwanza, Jackson Sikamo
"The Zambian Copper mining industry as we know it today has its genesis from early in the 20th century in the 1920s. Consistent private sector-driven investment in the industry over a period of over 5
Jan 1, 2015
-
EQS: A Computer Software Using Fuzzy Logic For Equipment Selection In Mining Engineering
By A. Basçetin
Equipment selection in mining engineering is one of the most important decisions that affects the mine design, production planning and economic parameters in open pit and underground mining. Mine plan
Jan 1, 2006
-
Steel-Slag As Filler Material In Concrete
By H. Moosberg-Bustnes
In cement-based products, such as concrete and mortars, a balance between the particle sizes of the components must be kept in order to obtain the required material properties, such as workability and
Jan 1, 2004
-
Increasing efficiency of conveyor belt transporting system 4 Belt Lonmin - Synopsis
By G. G. le Roux
The purpose of the investigation was to assess various options for increasing the efficiency of the conveyor belt transporting system used at 4 Belt Shaft at Lonmin?s Marikana operations. The reason f
Jan 1, 2008
-
The Development And Implementation Of The Lonmin Mechanized Breast Mining
By K. Moxham, R. G. B. Pickering
Over the last few years Lonmin Platinum and Sandvik have embarked on a unique partnership of collaboration through a systematic approach to developing equipment to mechanize and automate narrow reef p
Jan 1, 2006
-
Lessons Learnt From Heap Leaching Operations In South America - An Update
By B. Ulrich
The basis of this paper is a compilation of work in the design and construction of copper heap leach facilities, and interviews with various heap leach operations personnel in Chile and Peru. The purp
Jan 1, 2003
-
2.3 Barnard - From Dust To Dust??
By P. Rice, A. Photolo, A. C. Barnard
Introduction -Sampling Tool Project (STP) -History -Results to date -Costs -Questions
Jan 1, 2005
-
Developments Of Mechanized Technologies For Low Seam Height Mining In Platinum
By P. Bracher
Most efforts to mechanize low seam (narrow reef) mining of platinum ore are presently based on board-and-pillar methods with1.6?1.8 m in reef excavation. This paper attempts to substantiate the benefi
Jan 1, 2003
-
Environmental Considerations In The Preparation Of Bankable Feasibility Documents - Introduction
By A. A. Smithen
There is an increasing awareness of the importance of including an assessment of environmental liabilities in the preparation of bankable feasibility documents. This means that environmental assessmen
Jan 1, 1999
-
Advanced Methods To Characterize Thermal Properties Of Quartz
By E. H. Myrhaug, K. Aasly, T. Malvik
Six different types of quartz and quartzites used as raw materials by ferroalloy plants have been investigated with respect to their thermo mechanical properties. In order to investigate the effect of
Jan 1, 2007
-
Composite Failure Mechanisms In Coal Measures? Rock Masses - Myths And Reality
By J. V. Simmons
Composite rock mass failures involve intact rock material as well as fracture and shear on existing defects. Experiences from open-cut coalmining in the Bowen Basin of central Queensland are that fail
Jan 1, 2006
-
A Quantitative Method for Selecting Renewable Energy Projects in the Mining Industry Based on Sustainability
By M. Mostert
Mining companies sponsor a range of non-core, corporate social responsibility projects to adhere to social and labour plans and environmental management prerequisites that form part of a mining licenc
Jan 1, 2014
-
Kinetic Studies On The Leaching Reactions In The Autoclave Circuit Of The Tati Hydrometallurgical Demonstration Plant
By B. D. Paphane
Since the commissioning of the Tati Hydrometallurgical Demonstration Plant (HDP), which produces Ni and Cu cathodes as well as Co salt from sulphide concentrate employing Activox® technology for leach
Jun 1, 2013
-
Project Report - Pillar Mining At No. 1 And 2 Sub-Shaft On Kloof Gold Mine
Paper written on project work carried out in partial fulfilment of BSc Engineering (Mining) The aim of this project is to determine whether certain pillars occurring within the no. 1 shaft and no.
Jan 1, 2005