Geotechnical Challenges of Pile Driving in a Marginally Stable Slope TERMINAL 46 APRON UPGRADE, PORT OF SEATTLE, WA
By Monique Nykamp
"INTRODUCTIONTerminal 46 is located just south of downtown Seattle, and is one of the Port of Seattle’s busiest container terminals. The Terminal 46 Redevelopment Project was undertaken to replace the
Jan 1, 2007
-
A Study On Performance Of Piles Based On Methods Of Installation
By Babu K. V., Samyukta P.
The energy demand in India is expected to show increasing growth in the next few decades. The oil companies in India are revamping the existing oil refineries as well as constructing new refineries ac
Sep 1, 2022
-
Optimization of Drilled Shaft Design for a Highway Bridge in Arizona Using Load Test Results (0a742001-9cf1-441f-b0fc-5890697ef97e)
By John C. Niedzielski, A. Frances Ackerman
The existing US-70 Bridge over the Gila River at Bylas, Arizona is planned to be replaced due to its current poor condition. The replacement bridge is planned to be a 15-span, 1,904-foot (580 meter) l
Jan 1, 2017
-
Guidelines for Soil Mixing
"1.0 INTRODUCTIONThese Guidelines reflect the state-of-the-practice of the Deep Mixing Method (DMM) in North America. DMM is an in situ mixing process that breaks down the soil structure; injects bind
Jan 1, 2016
-
p-y Curves For Analyzing Micropiles in Sandy Soils Using Lateral Load Test Data
By Mahdi Soudkhah, Akhter Hossain
Vertical micropiles are generally considered to be low in lateral resistance. Therefore, battered micropiles are often used when additional lateral load carrying capacity is required. However, batteri
Jan 1, 2019
-
Building Above And Excavating Below An Iconic Building In Manhattan
By John S. Civetta, Seth Martin, Marc J. Gallagher, Arthur J. Alzamora, Ronald Peralta
The Crown Building, built circa 1921, is a 26-story iconic building located at West 57th Street and Fifth Avenue in the heart of Manhattan. The paper highlights collaboration between the geotechnical
-
The Berkeley Art Museum: Repurposing a Historical Building
By Timothy Nelson, Simon Burnworth
"The Berkeley Art Museum and Pacific Film Archive (BAMPFA), which currently resides in a 1970s-era post-modern concrete structure just south of the University of California, Berkeley campus, was in ne
Jan 1, 2016
-
Guide to Drafting a Specification for High Capacity Drilled and Grouted Micropiles for Structural Support
By Donald Bruce
The three types of specifications which are used for micropile work are: ? Performance Specifications: The contractor is permitted control over certain design and/or construction procedures but must
Jan 1, 2004
-
Guide to Drafting a Specification for Micropiles (XXII International Mineral Processing Congress)
By Joint Micropiles Committee
"The three types of specifications which are used for micropile work are: • Performance Specifications: The contractor is permitted control over certain design and/or construction procedures but must
Jan 1, 2004
-
Challenges and Lessons Learned from Shoring Design of 2nd / Broadway Metro Station
By Babak Mamaqani, Pirooz Barar
Regional Connector Transit Corridor (RCC) is part of the Los Angeles metro expansion project under construction which adds three new stations into the system. PB&A was responsible for the design of th
Jan 1, 2019
-
Optimized Neural Network Model For The Prediction Of Driven Pile's Resistance
By Hyun. I. Park
Although numerous investigations have been performed over the years to predict the behavior and bearing capacity of piles, the mechanisms of these behavior and bearing capacity of piles have yet to be
Jan 1, 2006
-
Pile Driving Between the Amazonas and Xingu Rivers in the Tucuruí-Manaus Transmission Line – Lessons Learned and Solutions Found for a Challenging Project
By José Carlos do Amaral, Marcelo Groszownik, Jorge Beim
"Initiated in 2008, the project of this 1800 km long Electrical Transmission Line is a job of extreme technical complexity, crossing regions of major forests and rivers. When ready, it will allow the
Jan 1, 2015
-
Discussion of Differences in Design Methodology between Granular and Grouted Inclusions
By Brandon Buschmeier, Frederic Masse
"Inclusions are a type of ground improvement that provide an improvement of a soil mass by insertion of a material with better characteristics than the surrounding soils. There are primarily two types
Jan 1, 2015
-
State of the Art Ground Improvement Technique for a Residential Complex: Case Study
By Madan Kumar Annam, Hari Krishna Y, I. V. Anirudhan
"For completion of projects in time with positive results, improvements of productivity and effective project management procedures have become extremely important. This paper discusses a milestone pr
Jan 1, 2015
-
Pile Testing Methods - Authors' Presentations. - Paper 9.1 An Innovative Approach To Load Testing Of High Capacity Piles
By W. G. K. Fleming
Mr P. Bermingham introduced paper 9.1, describing the development and trials of a new pile load-testing technique that the Authors had termed "Statnamic". The system involved launching a test weight m
Jan 1, 1991
-
Seismic Remediation of Perris Dam
By Michael W. Driller, Wen Yan (Grace) Chen, Steven J. Friesen
"Remediation for Perris Dam has been proposed in response to deficiencies identified in a seismic stability study prepared by the California Department of Water Resources (DWR) in 2005. Lenses of pote
Jan 1, 2015
-
Helix Deflection Effect on Load Settlement Behavior of Pile with Increasing Stress Level
By Adnan A. Malik, Tadashi Maejima, Jiro Kuwano
"Previous studies revealed that the helix deflection reduced the end bearing capacity of screw pile in dense ground even if the installation process is completed with minimal soil disturbance. The ult
Jan 1, 2017
-
Drilled Shaft Acceptance Criteria Based Upon Thermal Integrity Profiling
By Garland Likins, Gray Mullins, George Piscsalko
"Quality control of drilled shafts is greatly dependent upon the practices of the site personnel. For drilled shafts cast under slurry, inspection of the hole prior to concreting is very difficult or
Jan 1, 2016
-
-
Integrity Testing of Drilled Displacement Piles at a Major Campus
By Mark D. Fuhriman, Parham Khoshkbari, Robert Fosse
Drilled displacement piles are becoming an increasingly common deep foundation choice for their relatively simple installation methods, applicability to a wide range of subsurface conditions, and vers