The Impact of Commissioning and Start-Up Performance on a Mining/Metallurgical Project
By Jan E. Nesset, Phillip J. Mackey
"Studies have shown that there is a correlation between commissioning and start-up time, i.e. time to reach full plant design capacity, and the degree of innovation and technical/engineering uncertain
Jan 1, 2003
-
Barrick Goldstrike Grinding Expert System
By Steve Custer, Tim Kahl, Sue Parker
"The primary objective of the Barrick Goldstrike expert system is to achieve the desired liberation size for the autoclave circuit while maximizing throughput. In addition, when downstream limitations
Jan 1, 2001
-
Effect of environmental variables on pitting corrosion
By S. Rajeswari, D. Gopi
"Pitting corrosion inhibition of 304 stainless steel (SS) in groundwater with a ternary inhibitor mixture (phosphonic acid + bivalent cation + various surfactants) was studied with different environme
Jan 1, 2003
-
Stacking of Potash Mill Tailings (a53a3fa3-c9c5-495d-81ff-6d030f92ec59)
By P. G. Roden, G. A. Maki, P. J. Fullmann
"In October 1984, Rocanville Division began using a stacking system to handle potash mill tailings. Previous to this date, mill tailings were slurried to the top of the tailings pile and allowed to de
Jan 1, 1986
-
Process Improvements at Placer Dome Campbell Mine
By K. Norris
"The Campbell mill has undergone numerous changes over the past 43 years. However the rate of change has increased significantly in the last 4 years. A new grinding circuit, carbon-in- pulp circuit, p
Jan 1, 1992
-
Process Improvement Update at Brunswick Mine
By Jodi Roberts, Curtis Deredin, Jean-Guy Paulin
"Since the establishment of the Six Sigma quality improvement program in 2001, several projects have been successfully carried out in the copper-lead, zinc, copper separation, lead upgrading and bulk
Jan 1, 2008
-
Numerical Modeling of Standard Rock Mechanics Laboratory Tests using a Finite/Discrete Element Approach
By S. Stefanizzi
In the present paper, numerical simulations based on a finite/discrete element approach are used to study deformation and failure process during standard rock mechanics. FEM/DEM modeling has been used
May 1, 2009
-
Stratigraphic and Structural Constraints on Limestone Exploration: A Case Study from Northern New Brunswick, Canada
By I. Dimitrov, S. R. McCutcheon
"Industrial-grade limestone is found in both the Lower Silurian La Vieille Formation and Upper Silurian LaPlante Formation of the Chaleurs Group in northern New Brunswick. Currently, between 150 000 a
Jan 1, 2007
-
Haile Gold Mine Metallurgy and Flowsheet Review
By P. Tittes, M. Deal, M. Spicher, S. McDaniel, J. Wickens
"Haile Gold Mine is located near Kershaw, South Carolina, approximately 50 miles south of Charlotte, North Carolina. Gold was first discovered at the site in 1827, and the property has been through se
Jan 1, 2013
-
Framework for optimizing components in an oilwell cement slurry design
By D. Getzlaf
"Oilfield cementing has been utilized in the industry since the turn of the century. Originally, wells were shallow and criteria for well integrity were somewhat limited. Since that time, wells have s
Jan 1, 2004
-
Paste Fill Design at the Louvicourt Mine
By Pierre Lacombe
"The operation of the Louvicourt Mine will have to rely on stringent grade control and on the optimization of the amount of blocked ore made available per given development effort. All of the above be
Jan 1, 1995
-
Evolving Equipment Health, a Rio Tinto Case Study
By Daniel D. M. Adams
Over the last 100 years industry in general has been trying to advance the ability to maintain systems through management processes. Mining has looked to utilize onboard data systems in our mobile min
May 1, 2011
-
Overview of overburden removal at Syncrude Canada Ltd.
By Y. P. Malhotra, JE. C. Carter
"Syncrude's overburden removal requirement ranges from 20 million to 30 million bank cubic metres per year to meet tarsand demands for the production of 129,000 barrels of synthetic crude oil per
Jan 1, 1983
-
Geostatistical Determination of Production Uncertainty: Application to Pogo Gold Project
By J. A. McLennan
Geological uncertainty is an unavoidable characteristic of all mining projects since only limited information is available from sampling. Mine planning and development decisions with significant econo
May 1, 2004
-
The use of Personal Computers at Kidd Creek for Process Data Monitoring and Analysis
By Gordan Marrs, O. Matwijenko
"The Kidd Creek metallurgical site has been highly integrated to maximize revenues from its base metals mines. The site's operations include a Concentrator processing 4.3 million tonnes per year of co
Jan 1, 1989
-
Case Studies in the Use of the Falcon Gravity Concentrator
By S. McAlister
"Falcon Concentrators Inc. has developed a high capacity centrifuge for the recovery of fine, free gold as well as other metals and minerals which were previously thought to be unrecoverable by gravit
Jan 1, 1992
-
Population Statistics of Gold Nanoparticle Morphologies Determined by HREM Observations
By Kenji Koga
In order to derive the population distribution of gold nanoparticle morphologies as a function of size, highresolution electron microscopic (HREM) observations and structural analyses were done for ov
Oct 1, 2003
-
CIP - Who Needs It? A combination circuit of Gravity, Flotation and Intensive Leach may provide the Optimal Environmental and Cost Outcome for Gold Plants.
By Garry Johansen, Andrew McCallum, Sandy Gray, Gary Patrick, Jennifer Abols
"The authors challenge the traditional thinking that whole ore cyanidation followed by Carbon in Pulp (CIP) or Carbon in Leach (CIL) should be applied as a standard process in the majority of gold pro
Jan 1, 2003
-
Development and Implementation of an Operating Concept and Training Program for the Start-Up of the Stanleigh Mill
By H. Ewaschuk
"INTRODUCTIONRio Algom's Stanleigh Mill in Elliot Lake began production in June of 1983. The highly instrumented mill treats uranium ore at an average rate of 3900 metric tons per day. To help ensure
Jan 1, 1985
-
Géologie et géochimie de la mine Lamaque, Val d'Or, Québec
By Paul Bedard, Réal Daigneault, Guy Perrault
"La mine Lamaque est située a Val d'Or, Québec; les roches hônes appartiennent au groupe de Malartic, partie supérieure, et sont des andésites et des pyroclastites. On y retrouve deux formes d&ap