    Load Testing High Capacity Drilled Shafts - Summary

    By Jorj O. Osterberg

    Until ten years ago, the largest load tests on drilled shafts (bored piles) were about 3,000 tons (27MN). These tests were made with kentledge (large weights, usually concrete blocks) stacked up as a

    Jan 1, 2002

  • DFI
    High Risk Control For Piling And Deep Foundations - A Systematic Approach

    By Martin van Staveren

    In today's rapid changing construction world, the business pressures on piling and deep foundations reach sky-high levels. Ever increasing complexity of construction projects do severely contribu

    Jan 1, 2006

  • DFI
    Micropile Foundation Retrofit Design For Richmond-San Rafael Bridge, Richmond, California - Introduction

    By Patrick E. Durnal

    The Richmond-San Rafael Bridge was built in the early 50s' and was first opened to traffic on August 31, 1956. Among California's longest steel bridges, it spans more than 21,000 feet across

    Jan 1, 1998

  • DFI
    Experiences Of The Cast-In-Situ Pile Filling In Stone-Line Intercalation

    By Guan Jichang

    An abandened breakwater, located at the rear of No. 2 berth in Dongdu Port area of Xiamen City, was not cleaned thoroughly when the backfilling of sand started. The uncleaned stone layer was about 2 t

    Jan 1, 1991

  • DFI
    Ground Movements - A Hidden Source Of Loading On Deep Foundations (211df4c9-c07d-4182-8335-8f47bcc59b12)

    By Harry G. Poulos

    Ground movements can arise from a large number of sources and can have a significant effect on nearby piles and deep foundations. The loading of the piles by ground movements is a different mechanism

    Jan 1, 2007

  • DFI
    Woodrow Wilson Bridge Cofferdams (ef6ed0b3-5c8c-41f1-8337-00ee57bff823)

    By Roderic A. Ellman

    The new Woodrow Wilson Bridge (WWB) will replace the existing bridge over the Potomac River to connect Alexandria, Virginia to Prince Georges County, Maryland. The new WWB will extend approximately 1.

    Jan 1, 2013

  • DFI
    Recent Advances In Soil Nailed Earth Retention

    By Tom A. Armour

    Different variations of soil nailing techniques have been used in the United States since the late 1970's. Such techniques owe their origins to French developments, which began in the early 1970&

    Jan 1, 2003

  • DFI
    111,000m Of Continuous Flight Auger Piling For LNG Tank Bases In Poor Alluvial Soils, Isle Of Grain, UK

    By Shane Baker

    Cementation Foundations Skanska Ltd encountered many significant challenges in designing and constructing the foundations for the LNG (Liquefied Natural Gas) tanks and associated structures at the Isl

    Jan 1, 2006

  • DFI
    Evaluation Of Design Methods For Tieback Retaining Walls In Seattle - Introduction

    By John P. Turner

    The behavior of tieback retaining walls depends on many factors, including soil properties, groundwater conditions, construction sequence, spacing and stiffness of tiebacks and soldier piles, tieback

    Jan 1, 1990

  • DFI
    Present To Future Design Considerations Of Deep Foundations ? 1. Introduction

    By William S. Gardner

    It is certainly an honor to have been invited to address the Deep Foundation's Annual Meeting on such a vast and weighty topic as "Present to Future Design Considerations of Deep Foundations." Ac

    Jan 1, 1991

  • DFI
    Improved Pile Economics: High Design Stresses And Remote Pile Testing

    By Jim Frazier

    Tradition has often dictated low design load stresses on piles. Such traditions often developed prior to modern static or dynamic pile testing methods and perhaps result from a few limiting situations

    Jan 1, 2002

  • DFI
    New Technologies For Quality Control Of Augered Cast-In-Place Piles

    By Tracy Brettmann

    In recent years the Augered Cast-In-Place (ACIP) Pile industry has seen a substantial increase in the quality control options available to Contractors, Engineers, and Owners. Quality control methods r

    Jan 1, 2000

  • DFI
    Challenges And Uncertainties Relating To Open Caissons

    By Fathi Abdrabbo

    Open caissons are used for many geotechnical engineering applications. Open caissons may be used as deep foundation elements bypassing weak soils to tip in firm deeper strata, and in rivers and mariti

    Jan 1, 2012

  • DFI
    Excavation Bracing Technology ? Synopsis

    By G. F. Sowers

    Excavation bracing is a special structural system. It is built from the top down. The design is controlled by the economical construction of another structure as well as by the movement of the ground

    Jan 1, 2010

  • DFI
    Lateral Load Test on Piles with Large Free Stand

    By P. V. Chandramohan

    "In ports, piled berths are designed and constructed for berthing of ships with a finite draught. Piles in a bridge foundation also have a large free stand above scoured level. The piles of these stru

    Jan 1, 2015

  • DFI
    Use Of Nondestructive Testing To Evaluate Defects In Drilled Shafts: Status Of FHWA Research - Background

    By Clyde Baker

    Drilled shafts for many situations offer an economical alternative to driven piles. The Federal Highway Administration (FHWA) has spent considerable time and money in research and developing design an

    Jan 1, 1989

  • DFI
    Business Benefits Of An Integrated CFA Rig Instrumentation System

    By Jason N. Scott

    CFA piling is a ?blind? construction process that relies heavily on the rig instrumentation to produce sound piles. If the data measured and recorded during construction can be made available to engi

    Jan 1, 2006

  • DFI
    Fundamental Tests On The Performance Of High Capacity Pin PilesSM

    By Donald A. Bruce

    Pin Piles are small diameter, bored, cast-in-place piles used to underpin structures. They were first employed over 40 years ago in Italy, and have been used in the U.S. since the late 1970's. Ho

    Jan 1, 1993

  • DFI
    An Investigation of Grouted Pile Capacity Using Instrumented Pile Load Tests

    By Hayel M. El-Naggar, Sherif A. Akl

    Although grouted piles have been used for several decades since the idea was proposed in the 1970s, their design is mostly based on experience and unpublished proprietary methods. There is little rese

    Jan 1, 2018

  • DFI
    High-Strain Dynamic Testing Of Drilled Shafts And Cast-In-Place Piles

    By Garland E. Likins

    High-strain dynamic testing of drilled shafts and cast-in-place piles has become routine procedure in many parts of the world today. Field testing is performed by measuring strain and acceleration rec

    Jan 1, 1995