Numerical Simulations of Bulk Handling in Screw Conveyors by Three-Dimensional DEMBy P Cundall
Three-dimensional DEM (Distinct Element Method) simulations were conducted in order to examine the performance of screw conveyors, which are installed to transport bulk materials as parts of many indu
Jan 1, 2000
-
Small Pilot Plant Trials of Sirosmelt Copper SmeltingBy Grace NC, Lightfoot BW
Small scale trials of the smelting of a copper concentrate in the Sirosmelt submerged lance reactor are described. Pellets of concentrate were dropped into the reactor while injecting air-rich mixt
Jan 1, 1980
-
The Nature and Origin of the Ore Minerals of Mount MorganSome thirty ore minerals occur in the Mount Morgan orebody. Pyrite is the dominant mineral with chalcopyrite, magnetite and pyrrhotite major components. Gold and gold tellurides, in accessory amoun
Jan 1, 1974
-
Implementing Process Design Changes in Process PlantsThe resource sector is conservative industry and people are resistant to change. The methods and procedures used to implement changes in process plants ultimately determine the success of such changes
Jan 1, 2009
-
Prediction of Time Dependent Factors in Acid Mine DrainageBy Murray G
This paper outlines the processes involved in acid generation from sulphides and the key factors in identifying and predicting time dependent changes in the nature of acid mine drainage (AMD). The
Jan 1, 1988
-
Gold Recovery from Golden Spec Stibnite Concentrate by Aqueous Pressure TechniquesBy Williams C
A stibnite concentrate from Golden Spec (WA) was subjected to a series of tests involving high pressure cyanidation and pressure oxidation followed by conventional cyanidation. The concentrate, whos
Jan 1, 1992
-
The Use of Nitrogen Intertisation in the British IslesThe problem of spontaneous combustion has long exercised the minds of Mining Engineers. The idea of inertising an area with a non combustible gas has seemed to be an attractive way to overcome the
Jan 1, 1988
-
The Application Of Bore Core Data To Coal Preparation Plant DesignBy Arnold J. J
The design of a coal preparation plant using bore core data cannot be discussed without some reference to the wider considerations of design. A thorough knowledge of coal preparation processes and
Jan 1, 1977
-
Concepts of Sedimentary Basins: The Evidence of Oil and Gas FieldsGeosynclines have been well studied for many years, but very little has been written about the concepts of sedimentary basins in spite of the vast amount of data available. They have been regarded
Jan 1, 1987
-
Resource Optimisation With SimulationBy A Ruotsalainen
Mining industry sees a comprehensive future in optimisation and process control. High resource utilisation is a starting platform when lower operational costs with higher rate of return are the target
Jan 1, 2003
-
The Environmental Factor in the International Mining Development EquationBy Opitz E. A
The integration of environmental and permitting strategies into development has become a routine part of doing business for the international minerals industry. Paralleling the development schedule
Jan 1, 1997
-
Design of Very Large Mill Installations: Mill Design Specifications and AuditsA standard practice of auditing mill designs has developed in the mining industry. The purported aim of this task is to ensure that the mill being offered conforms to the design specification, thus re
Jan 1, 2002
-
Planning, Design and Construction of a Small Multi-use Tunnel in an Urban EnvironmentThe planning, design and construction of a service tunnel, under a major arterial road between two hospitals are described. The multiple uses of the tunnel combine to provide a favourable cost-benef
Jan 1, 1981
-
Celestite Ore Upgrading - From Laboratory to MillBy Joussemet R, Fabre F
The paragenesis of the Escuzar Mine (Andalusia-Spain) comprises: ò major constituents: celestite and carbonated minerals (abundant calcite and less frequent strontianite). ò minor constituents: sulph
Jan 1, 1993
-
The Geology and the Highly Selective Open Cut Mining Method of the Small, Irregular, Narrow and Low Grade St. George Orebodies at Mount MagnetThe St George orebodies are situated within the tectonically disrupted eastern limb of the Boogardie Syncline.Highly disturbed rafts of banded chert formations occur within a sequence of felsic volcan
Jan 1, 1984
-
The Stabilization of Arsenic by Its Incorporation Into Lead-Zinc Smelter SlagBy Lawson F
Arsenic-containing waste was dissolved into molten slags and the leaching behaviour of the quenched arsenic-doped slags (containing up to 2.3 wt per cent arsenic) was ascertained to evaluate the poten
Jan 1, 1996
-
Fluid Inclusions and Sulfur Isotopic Studies from a Possible Southeast Extension of the Toyoha Polymetallic Deposit, JapanFluid inclusions and sulfur isotopic compositions were studied in a possible extension of the Toyoha polymetallic vein deposit. The objective of this work was to gain a better understanding of the ore
Jan 1, 2002
-
The Rawas Gold Project æSuccessfully Overcoming the ChallengesÆ -- The Task Facing a Junior in Indonesia from Exploration to ProductionBy Williams JK, Bolitho BC
Laverton Gold NL (Laverton) is the first junior Australian mining company to establish a viable mining operation in Indonesia. It successfully commissioned the Rawas plant in Sumatra this year with an
Jan 1, 1997
-
Spraying the Surface or Just Scratching the Surface ù What Are the Real Benefits of In-Cycle Fibrecrete?Through the use of structural analysis programs such as Unwedge and considering the shear strength of applied fibrecrete it can be shown that fibrecrete can provide a higher factor of safety in a ætyp
Jan 1, 2005
-
Blair Anthol Coal Mine Project a Case History in Planning and ManagementBy Maxwell HW
Pacific Coal Pty Limited (a wholly owned subsidiary of CRA Limited) managed the interests of six members of a joint venture formed to mine and export eight million tonnes of export quality steamin
Jan 1, 1986