Creative Shoring Solutions For A Tight Urban SiteBy David G. Winter
The Olive 8 excavation site in Seattle was surrounded on three sides by conditions requiring innovation, careful modeling, and extensive instrumentation to support use of a first-of-its-kind shoring s
Jan 1, 2009
-
Augered Cast-In-Place Piles Deep Foundations Institute (DFI) 1988 Annual Meeting - Ritz-Carlton Hotel In Atlanta (Buckhead), GeorgiaBy James J. Neate
The augered cast-in-place pile system came into use in the late 1940's where various techniques were tried using pressure grouting methods. In the early development stages some piles were install
Jan 1, 1988
-
Seal Slab / Steel Pile Interface Bond From Full-Scale TestingBy Gray Mullins
This paper presents results from model and full-scale tests to assess the interface bond between a cast-in-place concrete seal slab and steel H-piles in cofferdams. Three different seal slab placemen
Jan 1, 2013
-
Complex Piling Works At London Blackfriars StationBy Jamie D. McEwan
To cater for the future introduction of 12 car trains, London Blackfriars railway station is being extended from the north end to span across the River Thames. Following the demolition of existing bui
Jan 1, 2011
-
Special Foundation Systems - Paper 2.1 - The Merits Of Polymeric Fluids As Support SlurriesBy K. Englehardt
J BERESFORD introduced the subject of the paper which is the use of polymeric slurries to support the sides of diaphragm wall and bored pile excavations during construction. In the opinion of the auth
Jan 1, 1991
-
Incorporating Set-Up Into Reliability-Based Design Of Driven Piles In Sandy SoilsBy Luo Yang
It has been known that after initial pile driving, pile capacity gain over time (set-up) could constitute a significant portion of the total pile capacity. In the past, there has been very little guid
Jan 1, 2006
-
The Alternate Technical Concept Process For Foundations At The New Mississippi River Bridge, St. LouisBy Dan A. Brown
The New Mississippi River Bridge (MRB) employed conventional design-bid-build procurement, but the bidding process included the opportunity for pre-qualified bidders to develop and propose confidentia
Jan 1, 2011
-
Construction Productivity Advancement Research Program (CPAR)By Jesse A. Pfeiffer
CPAR, the Construction Productivity Advancement Research Program, is a new initiative of the Corps of Engineers to enhance U.S. construction industry productivity through the development and applicati
Jan 1, 1989
-
Test Pile Program To Determine Axial Capacity And Pile Setup For The Biloxi Bay BridgeBy W. Robert Thompson
Hurricane Katrina caused significant damage to transportation structures on the Gulf coast in August, 2005, including the destruction of the US 90 Bridge over Biloxi Bay, Mississippi. Part of the suc
Jan 1, 2009
-
Experiences From The Italian High Speed Rail Network AV ConstructionBy Vincent Jue
In December 2009, the Italian High Speed Rail Network AV began running over the full 1000 km system length from Turin, at the foothills of the Alps to Salerno, on the seacoast south of the volcano Mt.
Jan 1, 2010
-
Recent Advances In Soil Nailed Earth RetentionBy Tom A. Armour
Different variations of soil nailing techniques have been used in the United States since the late 1970's. Such techniques owe their origins to French developments, which began in the early 1970&
Jan 1, 2003
-
Lateral Load Testing Micropiles To Evaluate The Impact Of Threaded Joints And Casing Embedment On Short Micropiles In Shallow RockBy J. Brian Anderson
Jointed micropiles were investigated to support bridge foundations where shallow rock was present. In this application, micropiles would have some amount of unsupported length, and would be subject t
Jan 1, 2011
-
Time-Dependent Bond Regain In Driven Piles In Permafrost ? SynopsisBy B. Ladanyi
The design philosophies for piles in unfrozen and frozen soils are compared, and their similarities and differences are underlined. It is shown that in frozen soils, the long term behavior of a pile i
Jan 1, 2010
-
Sonic Drilling Offers Quality Control And Non-Destructive Advantages To Geotechnical And Construction Drilling On Sensitive Infrastructure SitesBy John P. Davis
The use of conventional, circulatory air rotary and fluid rotary, cased and uncased drilling methods in the vicinity of sensitive infrastructure can have deleterious effects on the ground conditions s
Jan 1, 2006
-
Approach Wall Foundations Olmsted Locks And Dam Project ? SummaryBy Jeffrey A. Schaefer
The Olmsted Locks and Dam project is located on the Ohio River approximately 16.5 miles upstream of its confluence with the Mississippi River. It consists of twin 1200 ft. locks with floating and fixe
Jan 1, 2001
-
Simbat : High Strain Dynamic Test Of PilesBy Dominique Vié
Standards methods covers the procedures for testing deep foundation to determine the force and velocity response to an impact of a pile driving hammer or similar device. The results of analysis genera
Jan 1, 2002
-
-
Ultimate Skin Friction Of Single Batter Piles In Sand ? SynopsisBy A. M. Hanna
This paper presents the experimental investigation on the ultimate skin friction of batter piles. The model piles were pushed in medium dense sand deposits at different inclinations up to 30 with resp
Jan 1, 2010
-
Case History: Foundations For The New Mississippi River Bridge, St. LouisBy Paul J. Axtell
This case history describes the foundation design and construction for the New Mississippi River Bridge, presently under construction in St. Louis, Missouri. The 1,500 ft (457.2 m) main span of the c
Jan 1, 2011
-
Press-In Piling Technology For Sustainable ConstructionBy Philip Dubbeling
Conventional dynamic sheetpiling techniques are ill-suited to urban development because of the emission of excessive noise and ground vibrations. Drilled shafts and slurry walls alleviate some of thes
Jan 1, 2006