    Mini-Piling And Soil Anchors ? Introduction

    By Martin C. Jones

    This paper outlines the development of small diameter grouted piling, to deal with foundation problems in difficult soils conditions and in very restricted access areas. A number of applications are o

    Jan 1, 1987

  • DFI
    Mitigating Settlement with Pile-Supported Approach Slabs

    By Reda M. Bakeer

    "An approach slab is the roadway segment that immediately follows a bridge intended to provide a smooth transition between the two elements. Some approach slabs have developed rough rideability with t

    Jan 1, 2017

  • DFI
    Design And Construction Of An Earth Retaining Structure - Using A Pile In Self-Hardening Grout (PSHG) Wall

    By Allan Sylvester

    Construction of the Shot Tower Metro Station in Baltimore, Maryland was performed in two phases. In the first phase, a contractor was retained to excavate the station in order to construct twin tunnel

    Jan 1, 1997

  • DFI
    The Application Of The Caisson In China

    By Chen Xizhe

    The caisson is adapted to the foundation of concentrated heavy building. As there are the flowing sand, boulder or cobble and other serious obstruction, the open caisson can't sink, the caisson c

    Jan 1, 1991

  • DFI
    Driven Piles

    By S. Merjan

    Three papers were presented for discussion at the conference: 1) Instrumented driven steel tube piles at Canary Wharf; author: A. R. Gaba, United Kingdom. The author described the Canary Wharf

    Jan 1, 1991

  • DFI
    Design Of Foundation On Granular Piles For Five Storeyed Esidential Complex At Nazira, Assam - Synopsis

    By B. N. Hira

    A multistoreyed residential complex was at the penultimate stage of construction by ONGC at Nazira, Assam. The site was situated at high earthquake zone. The subsoil was very weak and contained soft t

    Jan 1, 1996

  • DFI
    Experiences With Heavy Drop Hammer Testing Of Rock-Socketed Shafts

    By Frank Rausche

    Since the early 1980s, when the Road Construction Authority of Victoria authorized the dynamic proof testing of roughly 100 drilled shafts of 1.5 m diameter and typically 60 m length in Melbourne Aust

    Jan 1, 2006

  • DFI
    Discussion On Base Grouted Piles

    By V. M. Troughton

    Further pile load testing has been carried out at Canary Wharf to compare the performance of base grouted and ungrouted bored piles founded in the Thanet Sand. The testing regime included three prelim

    Jan 1, 1991

  • DFI
    Dynamic Analysis Of Follower Driven Piles For The Venice Flood Gate Project

    By Frank Rausche

    Without doubt, driven piles are the most economical deep foundation element for a nearshore environment, providing for high bearing capacities and stiffness, quick installation times, assured quality

    Jan 1, 2006

  • DFI
    An Improved Method For The Prediction Of Pile Bearing Capacity From Dynamic Testing

    By R. T. Stain

    Dynamic methods of load testing piles using a drop hammer to generate the input force have been in use for many years. These systems are based on the wave equations developed at the Case Institute of

    Jan 1, 1989

  • DFI
    FDOT Method of Independent Separation of Tip and Skin Capacities of Driven Concrete Pile with Embedded Sensors

    By Sastry Putcha, Vamshi Vemula, Aneesh Goly, Kumar Allady

    Current dynamic testing practice to obtain pile total capacity will not yield optimum capacity due to the strain incompatibility between the side and tip resistances during driving. Superposition of e

    Jan 1, 2018

  • DFI
    New CIGMAT Downhole Penetrometer (DHP-CIGMAT) For Use During Drilled Shaft Construction

    By C. Vipulanandan

    It is critical to monitor the ground conditions during excavation and drilling of boreholes during construction to identify possible changes in the soil and rock formations. Drilled shafts are increas

  • DFI
    SFMOMA Expansion – Multiple Uses of Ground Improvement – A Case Study

    By Scott A. Walker, Frank L. Rollo

    "The San Francisco Museum of Modern Art (SFMOMA) in downtown metropolitan San Francisco, California, is supported on a mat foundation. Although the mat foundation of the original museum was designed t

    Jan 1, 2014

  • DFI
    Stresses And Settlement In Soil Due To Axially Loaded Piles And Pile Group - Synopsis :

    By Virendra Singh

    The load settlement behaviour of single pile or pile group may be obtained using computer based methods such as the finite or boundary element techniques. An alternative method of obtaining the vertic

    Jan 1, 1996

  • DFI
    A New Method Of Analysis Of Pile Displacement In Soil With Respect To Time

    By M. England

    A method for the analysis and prediction of single pile displacement behaviour is described. It is the displacement in time, under constant load, based on the use of hyperbolic functions to characteri

    Jan 1, 1993

  • DFI
    Test Pile Program Carrier Pier And South Wharf Naval Station Puget Sound Everett, Washington

    By David G. Winter

    The first test pile for the carrier pier and south wharf at NAVSTA Puget Sound was driven on December 27, 1989, and the final pile was tested on February 26, 1990. Implementation and modification of t

    Jan 1, 1990

  • DFI
    Helical Pile Foundation Anchors As A Practical Alternative

    By Dilip Khatri

    Helical pile anchors have gained acceptance over the past sixty years. Most recently they have been commonplace in the 20th century for the power utility industry in anchoring transmission towers, equ

    Jan 1, 2003

  • DFI
    Man - Organisation - Technology - Proposals For Optimising Preventive Work

    By Walter Ensinger

    Working safely means working cost-effectively. Every "dangerous occurrence" and - even more so - every industrial accident causes disruptions in the planned course of construction. Besides moral and l

    Jan 1, 2006

  • DFI
    Diaphragm Walls And Barrettes For Top-Down Construction: A Project Report

    By Bjöm Böhle

    Top-down construction (or cut and cover construction) is providing important advantages when comparing with conventional construction techniques for commercial developments with deep basements, underg

    Jan 1, 2006

  • DFI
    An Investigation of Grouted Pile Capacity Using Instrumented Pile Load Tests

    By Hayel M. El-Naggar, Sherif A. Akl

    Although grouted piles have been used for several decades since the idea was proposed in the 1970s, their design is mostly based on experience and unpublished proprietary methods. There is little rese

    Jan 1, 2018