Process Development for Milling B-Zone Ore at Rabbit LakeBy S. Dicarlo
"In late 1985, B-zone ore was first processed through the Eldor Mines mill at Rabbit Lake. Extensive modifications had been completed in order to mill this ore. In-plant process development was initia
Jan 1, 1988
-
Process Development For Recovery Of Lead As Lead Monoxide From Lead-Bearing WasteBy Sui Xue
A process has been developed from laboratory-scale experiments for the aqueous processing of various lead-bearing wastes. The process exploits the limited solubility of lead in sulfate-rich solutions
Jan 1, 1996
-
Process Development For Selective Flotation Of Silver, Zinc, And Tin From Huari-Huari OreBy J. L. Coburn
The Huari-Huari ore body is located in Southern Bolivia, at an elevation of approximately 3,800 meters above sea level. The ore is a complex massive sulfide, slightly marmatitic sphalerite, in a fault
Jan 1, 1977
-
Process Development for the Marampa Iron Ore Tailings Project, Sierra LeoneBy P Dunn
Following civil war in Sierra Leone, London Mining Plc obtained the mining license in 2006 and commenced activity to redevelop the Marampa mining and processing operations. The Sierra Leone Marampa mi
Jul 11, 2011
-
Process Development For Value-Added Products From Primary Kaolin Resources In MinnesotaBy M. S. Prasad
In earlier work it has been shown that paper filler clay products can be obtained from primary kaolin deposits of Minnesota. The objective of the current work was to reduce silica and iron contaminant
Jan 1, 1991
-
Process Development Metallurgical Studies for Gold Cyanidation ProcessBy S. Acar
"In recent years the gold mining industry has been challenged by declining metal prices as well as having to treat ores that have low grades and are refractory in nature. Many factors must be consider
Jan 1, 2016
-
Process Development of Victorian Brown Coal LiquefactionBy Matsumura T, Takematsu T
The Brown Coal Liquefaction Process (BCL Process) has been developed by Nippon Brown Coal Liquefaction Co., Ltd. (NBCL), and a 50-ton-per -day Pilot Plant has been partially completed and put into
Jan 1, 1987
-
Process Development: Recovery of Cobalt, Gold and Bismuth from Polymetallic Concentrates-NiCO Deposit, NWT, Canada-Part 1: LeachingBy A. Mezei
Samples of cobalt and bismuth concentrates produced from the NICO deposit in Northwest Territories were subjected to a comprehensive metallurgical testwork consisting of: pressure oxidation, ferric ch
Jan 1, 1999
-
Process Developments At Tailings Leach PlantBy Martin Banda, Gift C. Chisakuta, Moses Chabinga
KCM made a major modification to the Nchanga Tailings Leach Plant (TLP) changing the circuit from feeding post leach thickeners in parallel with leach discharge for solid ?liquid separation to a Count
Jan 1, 2005
-
Process Developments For Producing Tighter Tolerance Sbq BarBy Patrick E. Connell
During the ABM Conference of 2015 the latest design and process features of the new 3-roll RSB® generation were presented together with a unique Size Control System SCS® for a real time closed loop co
Oct 30, 2017
-
Process Developments in Pressure Die Casting of Zinc Alloys - Towards the Year 2000Zinc alloy castings continue to account for a very large, world-wide end-use market for zinc. However, an ever expanding multitude of other materials and processes are increasingly providing viable,
Jan 1, 1993
-
Process Developments in the Cobalt Purification Circuit at Chambishi RLE Cobalt Plant of ZCCM, ZambiaBy A. S. Rao
In the original roast-leach-electrowin (RLE) circuit at the Chambishi Cobalt Plant, commissioned in 1978, the separation of nickel and zinc from cobalt in aqueous streams was achieved by successive st
Jan 1, 1993
-
Process Diagnosis using Quantitative MineralogyBy Lori Kormos, Jhonny Carrión De la Cruz, Dominic Fragomeni, Elizabeth Whiteman, Jorge Oliveira
"Process diagnosis, flowsheet design and optimisation are most effectively and efficiently achieved through the use of metallurgical testwork combined with more modern quantitative mineralogical techn
Jan 1, 2010
-
Process engineering evaluation of lignite upgrading technologiesBy Adam J. Szladow
"INTRODUCTIONThe low calorific value and the high moisture and ash contents of run-of-mine (r.o.rn.) lignite limits the utilization of Saskatchewan lignites to thermal power plants in Saskatchewan, Ma
Jan 1, 1989
-
Process Engineering in Froth FlotationBy A. Vien, A. J. Neale, B. C. Flintoff, R. P. Edwards
Froth flotation is one of the most widely used and effective processes for mineral beneficiation. First introduced in 1911, flotation technology has seen many developments over the past 80+ years. Inn
Jan 1, 1994
-
Process Engineering Of Flotation Circuits No.34By R.P. Edwards, B.C. Flintoff
Froth flotation is one of the most widely used and effective processes for mineral benefication. First introduced in 1911, flotation technology has seen many developments over the past 80-plus years.
Jan 1, 1995
-
Process Evaluation and Flowsheet Development for the Recovery of Rare Earth Elements from Coal and Associated By-ProductsBy J. Herbst, J. Groppo, A. Noble, R. Q. Honaker
"Coal and coal byproducts produced annually contain a sufficient amount of rare earth elements (REEs) to meet current U.S. demand. The REEs exist in the form of minerals, ion-adsorbed elements associa
Jan 1, 2017
-
Process Evaluation and Flowsheet Development for the Recovery of Rare Earth Elements from Coal and Associated ByproductsBy J. Herbst, J. Groppo, A. Noble, R. Q. Honaker
"Coal and coal byproducts produced annually contain enough rare earth elements (REEs) to meet current U.S. demand. The REEs exist in the form of minerals, ion-exchanged elements associated with clays
Jan 1, 2017
-
Process Evaluations For Uranium Recovery From Scrap MaterialBy B. R. Westphal
The Integral Fast Reactor (IFR) concept being developed by Argonne National Laboratory is based on the pyrometallurgical processing of spent nuclear metallic fuel with subsequent fabrication into new
Jan 1, 1992
-
Process flow sheet development for the Corridor Sands ProjectBy L. Rademeyer, P. Mazzoni, C. Kubank, F. Brown
The Corridor Sands deposits of heavy mineral sands represent the largest known economic resource of titanium dioxide minerals. The West Block of Deposit 1 alone contains Measured and Indicated Mineral
Jan 1, 2003