    Recycled Polymer Application During Pile Boring Operations: A Review

    By Hitendrabhai S. Dewangan, Dr. Aashish A. Mehta

    Pile foundation is widely used in construction of marine structures. In offshore & marine piling work, drilling/boring supporting fluid is used to stabilize the borehole (excavation) prior to tremie c

    Sep 1, 2022

  • DFI
    Foundation Reuse And Strengthening Works At 65 And 67-69 Whitfield Street, London

    By Shields H. Arup

    The paper describes the innovative foundation reuse and strengthening works for two buildings in Central London. A 1950s building on piled foundations (65 Whitfield St) and a 1930s building (67-69 Whi

    May 1, 2022

  • DFI
    Rocky Mountain Arsenal Section 36 Lime Basin Soil Remediation Project – Seepage Barrier

    By A. David Miller, Douglas M. Barber

    "The Rocky Mountain Arsenal was used by the military to produce chemical warfare agents and incendiary munitions for use during World War II and later by private companies for the production of indust

    Jan 1, 2015

  • DFI
    Accumulated Rotations of Bucket Foundations under Long-Term Cyclic Loads in Sandy Ground

    By Sung-Ryul Kim, Woong-Jong Park, Juhyung Lee, Si-Hoon Lee

    "A bucket foundation has been considered to be a potential foundation technology for offshore wind turbines. In this study, a series of 1-g model tests were performed to analyze the accumulated rotati

    Jan 1, 2016

  • DFI
    Vibrations Caused by Pile Driving (bb4f9935-841f-4be3-bb1b-f95875d26e25)

    By K. Rainer Massarsch

    "Part 1 of 2 By K. Rainer Massarsch, Geo Engineering AB, Stockholm, SwedenINTRODUCTIONConstruction activities, such as driving of piles and sheet piles, soil compaction or excavation generate noise an

    Jan 1, 2004

  • DFI
    A DC Electrical Resistivity Method for Jet Grouting Column Diameter Quality Control with Case Studies from Grand Paris Project

    By Sina Z. Yekta, Zhangwei Ning, Pierre Frappin

    This paper describes a DC (direct current) electrical resistivity method, which uses the contrasts in resistivity measurements to estimate the diameter of jet grouted columns as soon as they have been

    Sep 8, 2021

  • DFI
    Micropiled Foundations of Telecommunication Towers

    By Racquel Nottingham, Marc Mastrantuono, Freddy Lopez

    In the digital era that we live in, connectivity and mobility play a decisive role in our daily activities. In this context, insufficient telecommunication infrastructure gives origin to the so called

    Sep 8, 2021

  • DFI
    Introduction (10b9df94-8559-46e8-b74a-5e5ae2f990b0)

    "The development of non-destructive testing (NDT) methods for deep foundations occurred in several parts of the world, gradually coming together into the present state of the art. The compilation of t

    Jan 1, 2004

  • DFI
    3D Analysis Of The Seismic Behavior Of Inclined Micropiles

    By Seyyed Mehdi Radeghi Mehrjou

    It is important to study structures and their retrofitting techniques in order to avoid earthquake-induced seismic damage within countries that are prone to earthquakes. Todays, micro piles are employ

    Sep 1, 2022

  • DFI
    Elimination of Environmental Footprint: LVCC Expansion - Foundation Installation

    By Zachary Q. Maassen

    Upon approval from the Las Vegas Convention and Visitors Authority (LVCVA), Turner/Martin Harris, A Joint Venture began construction on the estimated $860 million expansion for the Las Vegas Conventio

    Jan 1, 2019

  • DFI
    Automation Of Pile Foundation Design Post-Processing To Produce Pile Plans

    By Rajasekar Subbian, Jessica Oudhof

    In the Netherlands pile foundation design is done using CPTs in accordance with EC7 national annexure. The capacity per tip level is calculated for every CPT followed by zonation to find the tip level

    May 1, 2022

  • DFI
    Artificial Ground Freezing – A Typical Application for the Underpass of an Existing Metro Station in Rome

    By Bruno Vingiani, Alessandro Bertero

    "The use of Artificial Ground Freezing (AGF) for temporary soil strengthening and seepage control is an effective alternative to grouting when dealing with soils whose degree of finesses would imply t

    Jan 1, 1900

  • DFI
    Pre-engineered Hydraulic Bracing Systems

    By Braxton P. Erbe, Douglas C. Brunot

    A variety of systems and techniques exist to support deep excavations where sloping is not feasible. This paper will explore an example project involving the use of pre-engineered hydraulic bracing sy

  • DFI
    Brickworks Marketplace Ground Improvement, Adelaide

    By Andrew Middleton, Mark Wyatt

    "The Brickworks Marketplace Project is a significant shopping centre development in inner north west Adelaide constructed by Badge Constructions in 2014 and 2015. The site was a former brickworks with

    Jan 1, 1900

  • DFI
    Versatility of Compaction Grouting to Stabilize and Lift Large Structures

    By Joe Harris

    Large structures, such as a multistory office building or a large storage tank, are constructed the most economical way possible, which may involve a shallow foundation system placed on native soil or

    Sep 1, 2023

  • DFI
    Structural Evaluation of Thermal Integrity Profile Results of Transmission Foundations

    By Ryan Weaver, Travis Coleman

    The drilled shafts that support transmission lines and substations have been increasingly subject to testing to assess the integrity of placed concrete. Cross-hole Sonic Logging (CSL) has been used, b

    Jan 1, 2019

  • DFI
    A Case Study Describing The Use Of A Top Down Construction Sequence For A Three Level Basement Using A Diaphragm Wall And Cfa Foundation Piles

    By Chris Leach, Lucie Spencer

    This case study describes the geotechnical aspects of the basement construction for a multi-storey, residential and hotel complex located in the newly developed Elizabeth Quay precinct in Perth, Weste

    Nov 1, 2022

  • DFI
    Field and Laboratory Mix Trials for a Deep Soil/Cement/Bentonite Cut-Off Wall Using CSM Equipment

    By Russell J. Denny

    "A 25m deep cut-off wall is required for environmental remediation of a Former Chlor-Alkali Plant. Extensive trials were conducted to verify the effectiveness of the mixes proposed, with the requireme

    Jan 1, 2015

  • DFI
    Metro Sports Facility – A Ground Improvement Case Study

    By I. D. McPherson, Dominic P. Mahoney

    The Metro Sports Facility is currently under development in Christchurch, New Zealand and is a key Anchor Project in the city’s post-earth quake recovery. When completed it will be largest indoor spor

    Nov 1, 2022

  • DFI
    As-Built Analysis - An Integral Part Of Pile Foundation Design

    By Dan Yang

    Pile foundation designs are performed routinely based on geotechnical information available at the time of design, often with due consideration of large uncertainties inherent to soils and site condit

    Jan 1, 2010