Ground Improvement for the Distressed Earth Bund Using Stone Column - A Case StudyBy M. Kumaran, A. Vetriselvan, A. Purantharan
"This paper presents a case history of evaluating the stability of a distressed earth bund and rectification measures carried out. A 5.45 km long, 7m high earth bund for drinking water storage was con
Jan 1, 2017
-
Mechanical Characterization of a Chemically Stabilized Soft Soil Reinforced with Fibers When Subjected to Tensile SolicitationsBy J. M. N. P. C. Teles, Venda Oliveira P. J., Correia A. A. S.
"AbstractA laboratory work was performed to study the mechanical behavior of a Portuguese soft soil chemically stabilized with binders and reinforced with metallic fibers when subjected to tensile str
Jan 1, 2014
-
Effect Of Pressurized Drilling Methods On The Lateral Load Capacity Of Drilled Shafts - A Practical Insight And An Analytical ApproachBy Özgür Bezgin
This paper presents observations on the installation of drilled shafts from two construction projects and an academic study with experimental and analytical parts. The construction projects involved t
Jan 1, 2009
-
Kirkpatrick Street Pump Station Addition Excavation: Small Project, Big TwistBy James P. Stewart
This case history describes the engineering design and construction for the Contractor of a 35-ft-deep excavation for an 800-square-foot addition to an existing sewage pump station. The site posed une
Jan 1, 2003
-
The Silver Spring Transit Center: Design And Construction Of Drilled Shafts In An Urban EnvironmentBy James E. Parkes
The Silver Spring Transit Center is a new three-level transit center that will include bus loops for County, Metro and intercity buses, parking, and retail space. It replaces an existing bus station
Jan 1, 2011
-
Effects Of Helical Anchor Geometry On Long-Term Performance Of Small Wind Tower Foundations Subject To Dynamic LoadsBy Amy B. Cerato
The application of this study is to use helical anchors as a foundation system for small wind tower (1 ? 10 kW) guyed cables. Helical anchors are currently used to anchor guyed cables of telecommunic
Jan 1, 2008
-
Case History: Deep Soil-Cement Mixing At The I-90/I-93NB Interchange On The Central Artery/Tunnel Project, Contract C09A7 At Fort Point Channel Site, Boston, MA - SynopsisBy Robert Jakiel
The following paper is being presented to provide an understanding of the Deep Soil-Cement Mixing (DMM) performed at Contract C09A7 at the Fort Point Channel Site (FPC), for the I-90/I-93 Interchange
Jan 1, 2000
-
Deep Diaphragm Walls And Bored Piles For Subway Construction At The Amsterdam Central StationBy Wolf-R. Under
For improvement of urban traffic infrastructure, the City of Amsterdam is currently constructing the 9.5 km long North-South Metro line passing through the central districts of Amsterdam. Focal secti
Jan 1, 2006
-
Residual Loads Measurements in Driven Steel H-PilesBy Reda M. Bakeer
"Measurements obtained during load testing of two steel H-piles driven at a site in Northeastern Mississippi are discussed. The general site conditions, equipment used, testing procedures and results
Jan 1, 2017
-
Ground Movements - A Hidden Source Of Loading On Deep FoundationsBy Harry G. Poulos
Ground movements can arise from a large number of sources and can have a significant effect on nearby piles and deep foundations. The loading of the piles by ground movements is a different mechanism
Jan 1, 2006
-
Multiple Foundation Systems For The Porter Street Outfall Relocation For The North Approach - SummaryBy William D. Spielvogel
The Massachusetts Highway Department awarded the Porter Street Outfall Project to the J.M. Cashman Company in November 1991. Timely completion of the Project in one and one half years is critical to t
Jan 1, 1994
-
The World In Steel Sheet Piling ? SynopsisBy M. Dondelinger
This paper presents a comprehensive review of steel sheet piling including internationally manufactured hot rolled sections, their history, applications, installation and driving techniques. The di
Jan 1, 2010
-
25 Story Structure On River Flood Plain Soils Improved By Vibrocompaction And Compaction GroutingBy Frank Callanan
The Ameristar Casino expansion project included the design and construction of a 25-story hotel and 9-story parking structure expansion. The site is located in a floodplain on the banks of the Missour
Jan 1, 2009
-
Application Of, And Experience With, An Electronically-Controlled Hydraulic Piling Hammer ? 1 ? IntroductionBy D. Arentsen
Changing environmental laws, new operating requirements and the increasing accuracy with which the bearing capacity of driven piles can be calculated have all led to the development of hydraulic pilin
Jan 1, 1987
-
I-880 Replacement Project (Cypress Freeway) Large Diameter Driven Pipe Pile Foundations Test Program And Construction Test Pile Program - Indicator Pile Test Program - Field WorkBy Darrell L. Beddard
Pile driving started October 29, 1993 and was completed on January 27, 1994. Field work included driving piling from ground surface at one site and at or near proposed footing elevations for the remai
Jan 1, 1996
-
Extrapolation of Unit Side Resistance in Drilled Shaft Foundations Based on Bi-Directional Load Test DataBy Ramin Motamed, Joseph A. W. Toth
Evaluation of the capacity of large-diameter drilled shafts using current load test methods present challenges when considering the magnitude of loads required to fully mobilize their capacities. Ofte
Jan 1, 2018
-
High Stress Pile Testing At Soldier FieldBy Michael H. Wysockey
The load test program for the pile foundation at Soldier Field included static and dynamic load tests at four locations around the site. The dynamic tests were run with no knowledge of the static resu
Jan 1, 2002
-
Tied-Back Micropile Walls In Landslide RepairBy Kevin W. Cargill
In September 2004, Hurricanes Frances and Ivan caused the Pigeon River in western North Carolina to flood. This flooding eroded the embankment below Interstate 40 (I-40) and sent one of the eastbound
Jan 1, 2006
-
Design Of Drilled Shafts Supporting Sound WallsBy Ke Yang
Drilled shafts are widely adopted as the foundation for sound walls. However, there has been a lack of uniformity in design and analysis methods and design criteria, in terms of factor of safety again
Jan 1, 2007
-
Diaphragm Wall Construction, Instrumentation, and Testing for a Hydroelectric Power FacilityBy David Gatto, Nicolas A. Willig-Friedrich, Jeff A. Segar
"With the increasing demand for electricity, and requirements to generate this power cleanly, more producers are turning towards hydroelectric power. A project in Iowa currently under construction wil