Organization
  • DFI
    History Of Timber Piles And Preservation Techniques - A Presentation At The Deep Foundations Institute Annual Meeting Williamsburg, Virginia, December 1982

    By Bruce Haldeman

    Timber has been used as pile support for structures for 6,000 years. Some means of preservation of wood go back almost that far. Timber piles support all types of structures ? some are buried below th

    Jan 1, 1984

  • DFI
    Analysis Of Strain-Dependent Concrete Modulus From Mass Instrumented Test Pile Samples

    By Lee Sieng Kai

    This paper presents the result of the analysis of strain-dependent concrete modulus from full-scale static axial compression load tests conducted on more than 200 instrumented cast-in-place barrettes

    Jan 1, 2006

  • DFI
    Approach Wall Foundations Olmsted Locks And Dam Project ? Summary

    By Jeffrey A. Schaefer

    The Olmsted Locks and Dam project is located on the Ohio River approximately 16.5 miles upstream of its confluence with the Mississippi River. It consists of twin 1200 ft. locks with floating and fixe

    Jan 1, 2001

  • DFI
    Short Comparison Of The Determination Of Allowable Loads Of Steel H-Piles Following The Practice Applied In Different European Countries - Synopsis

    By L. P. Weber

    During the years 1983-1987, a research programme, jointly performed by the steel producers ARBED, British Steel Corporation, Peine-Salzgitter, Unimetal, and co-sponsored by the European Community for

    Jan 1, 1991

  • DFI
    A Study in Extreme Event Large Displacement Analysis of Large Diameter Piles

    By Bret N. Lingwall, Byron Foster

    The problem of reliable extreme event modeling of large diameter piles under enormous structural or kinematic loads has gained more attention in recent years. In particular, the soil response around t

    Jan 1, 2018

  • DFI
    Axial Pile Displacement Evaluations From Seismic Piezocone Data And Back-Analysis Of Load Tests

    By Fawad S. Niazi

    Ever since the use of the cone penetration test (CPT) in geotechnical practice, attempts have been made to correlate CPT parameters with pile capacity components of unit end bearing (qb) and unit shaf

    Jan 1, 2011

  • DFI
    Keynote Lecture: Axial Design And Lateral Design - Deep Foundations

    By Mike Neill, O&apos

    ? Bypass soft soils near the surface ? Resist uplift loads ? Resist lateral loads ? Bypass scourable soils ? Bypass liquefyable soils ? Mitigate movement of expansive or frozen soils ? "Tu

    Jan 1, 1998

  • DFI
    Copenhagen – Denmark Cityringen Metro Project: Innovative Solution for Deep Excavation in Complex Urban Areas

    By Paolo Cavalcoli, Marco Ziller

    "ABSTRACT: In the year 2010 the State of Denmark together with the Municipality of Copenhagen, launched a very important and complex Project : the complete construction of a new double Subway Line :th

    Jan 1, 2014

  • DFI
    Monitoring And Quality Control Of A 100 Metre Deep Diaphragm Wall

    By D. A. Bruce

    To check the feasibility and the quality of a very deep diaphragm wall, a tern of adjacent panels has been constructed, up to a depth of 100 m, in the Milan sandy gravelly soil by means of a hydraulic

    Jan 1, 1989

  • DFI
    Effective Dewatering Is More Than A Pump In The Hole - A Presentation At The Deep Foundations Institute Annual Meeting St. Louis, Missouri, November 1980

    By William J. Rothschild

    Ground water at construction sites can be controlled by properly placed wellpoint dewatering systems. Care must be taken in planning cofferdams to have adequate space for and access to pumps, headers

    Jan 1, 1984

  • DFI
    Seismic Retrofit Of Bridges; Geotechnical Design Considerations And Case History

    By Aly M. Mohammad

    State and federal agencies during rehabilitation of existing bridges may require the existing bridges to be evaluated under seismic conditions. If the bridge does not perform under the seismic event,

    Jan 1, 2006

  • DFI
    State Of The Art In Double Rotary Drilling - Experience Gained From Practice

    By Markus Schönit

    Double rotary drilling combines continuous flight auger drilling with a casing for producing a cast-in-place pile. When producing a pile an outer casing and an auger (hollow auger) rotating inside

    Jan 1, 2011

  • DFI
    Resolution Of Prestressed Concrete Pile Splice Problems - Summary

    By David Siu

    Many problems were encountered with the mechanical wedge-type splices used for the 15-inch square precast prestressed concrete piles installed at an industrial plant site. Many of the wedges were brea

    Jan 1, 1991

  • DFI
    Determination Of Design Pile Uplift Capacities Using Dynamic Pile Testing Methods

    By Juan M. Antorena

    A pile driving and testing program was undertaken to evaluate installation procedures, assess capacity, particularly in uplift, of 360- and 460-mm (14- and 18-inch) square prestressed concrete piles a

    Jan 1, 1995

  • DFI
    Testing And Evaluation Of Driven Plate Piles In A Full Size Test Slope: A New Method For Stabilizing Shallow Landslides ? Introduction

    By Richard Short

    Shallow rainfall-induced landslides in residual and colluvial hillslopes and steep embankments are a common occurrence in many settings [1, 2, 3]. While occasionally posing a threat to property and l

    Jan 1, 2007

  • DFI
    Pin Piles For Seismic Rehabilitation Of Bridges

    Since the 1989 Loma Prieta Earthquake in the San Francisco Bay Area, the California Department of Transportation (CALTRANS) has accelerated seismic upgrading of their bridges. Many structures can be i

    Jan 1, 1993

  • DFI
    The Quality Control Of Pile Foundations Of Tall Buildings In Shenzhen

    By Li Keqiang

    Among the pile foundations of the 156 tall buildings over 18 storeys in Shenzhen, 86. 5% of them are constructed by slurry drilled piles, bored piles and excavated piles (hand-dug caissons). Based on

    Jan 1, 1991

  • DFI
    Minipiles And Jet-Grouting: A Strong Foundation In Parma, Italy

    By Bruno Gemmi

    The objective of the ? 200 million ($280 million) project Parma Railways Station-Urban Transformation was the reconnection of the North and South parts of the town by constructing an 80 m (250 ft) wid

    Jan 1, 2011

  • DFI
    Recent Developments In Secant Bored Pile Wall Construction

    By D. E. Sherwood

    Recent developments in high torque hydraulic rotary rigs has lead to the construction of secant bored pile walls by rotary drilling methods in circumstances where earlier methods were difficult and in

    Jan 1, 1989

  • DFI
    Construction Of Effluent Outfall Diffusers For The Boston Harbor Project

    By Geoffrey D. Collins

    This paper deals with the construction of the Effluent Outfall Diffusers which form part of the outfall for the Deer Island sewage project. The work was executed 15 km out to sea in Massachusetts Bay

    Jan 1, 1994