    Developments of Pasminco Mining's South Concentrator

    At Pasminco Mining's South concentrator. which was commissioned in 1952. an expansion. modernisation and efficiency improvement program commenced in 1986 with a coarse ore stockpile and grinding

    Jan 1, 1991

  • AUSIMM
    Options for Concentrate Drying Technologies when Designing a Copper Smelter

    By H Lehtonen, H Mansikkaviita

    In primary copper smelters, the received copper concentrate and other materials contain a certain amount of moisture, ranging from six to 14 per cent. Moisture in wet concentrate has a negative effect

    Jan 1, 2006

  • AUSIMM
    Predicting Mill Ore Feed Variability Using Integrated Geotechnical/Geometallurgical Models

    By M Astorga, J Jackson, J Gaunt

    The Ban Houayxai mine (BHX) is a relatively low-grade, low-cost, open pit gold-silver deposit in Laos operated by Phu Bia Mining, a subsidiary of PanAust. The ore production rate at BHX is 4.5 Mt/a, w

    Nov 24, 2014

  • AUSIMM
    Quantification of surface sensor representivity of primary crushed ore for bulk ore sorting

    By J Rutter, D Francois-Bongarcon, M Federov, N Odiar, M Scott

    There are two fundamental methods for metalliferous sensing of primary crushed ore available for deployment at operations. These methods can be classed as surface measurement techniques (including XRF

    Nov 10, 2020

  • AUSIMM
    Optimising Flow in the Mining Value Chain

    By A Dunne, R Kruger, H Coleman, P G. Laurens

    External and internal challenges in mining are increasing the difficulty and complexity of operating mines. The external mining environment has a big impact on mining operations and is driving the foc

    Jul 13, 2015

  • AUSIMM
    Preparing for Uncertain Mineral Futures - A Survey of AusIMM Members on the Future Issues and Drivers for the Australian Minerals Industry

    By C Mason, A Littleboy

    This paper presents the results of a large scale survey of The Australasian Institute for Mining and Metallurgy (AusIMM) membership. This survey aimed to understand and define the key issues and drive

    Jan 1, 2009

  • AUSIMM
    Better Prediction of Performance of a Slope Using Time-series Monitoring Data at Multiple Points in a Multistep Excavation

    By L M. Zhang, X Y. Li

    Surface displacements are routinely monitored at multiple points during slope excavation. The monitoring data reveals the safety status of the slope under current loading conditions. They can be used

    Nov 5, 2014

  • AUSIMM
    Stochastic Optimisation of Mineral Value Chains – Developments and Applications for the Global Optimisation of Mining Complexes with Uncertainty

    By R Dimitrakopoulos, R Goodfellow

    One of the primary objectives when optimising a mining complex is to maximise its value for the primary stakeholders. In order to achieve this objective, it is necessary to holistically optimise all a

    Nov 24, 2014

  • AUSIMM
    Improving Pentlandite Pyrrhotite Separation at INCOÆs Clarabelle Mill

    By M Xu and, P F. Wells, A N. Kerr, Y Shields

    Triethylene tetramine (TETA) has been used in combination with sodium sulfite (sulfite) for pyrrhotite depression at Clarabelle Mill since 1998. This combination has been highly successful at reducing

    Jan 1, 2005

  • AUSIMM
    Lessons learnt from six mine disaster case studies to improve audit and assurance and ESG

    By A Atkins

    Six recent case studies were selected based on the eight main causes of mine disasters (Table 1; Quinlan, 2014) and where credible information sources, such as Royal Commission Reports, Coronial Inves

    May 5, 2022

  • AUSIMM
    Didipio - Learning the Lessons, Adapting and Getting Ready for Production

    By R Redden

    "The Didipio Gold-Copper project in the Philippines has been a well-defined reasonably high gold grade porphyry for almost two decades. OceanaGold are now bringing the project into production in late

    May 24, 2012

  • AUSIMM
    Why Reinvent the Wheel when there are Established Methodologies to Aid the Design and Assessment of Restored Natural Ecosystems on Mined Land?

    By R N. Humphries

    The aim of this paper is to question the need to develop bespoke monitoring and assessment methodologies and criteria, thereby ‘reinventing the wheel’, when designing and assessing the success of impo

    Jul 16, 2014

  • AUSIMM
    Kelsey Centrifugal Jig Implementation at Namakwa Sands for Zircon Recovery from Quartz Rejects

    By P V. A van der Westhuyzen

    Namakwa Sands is a heavy minerals mining and beneficiation business in the Exxaro Sands Division, and operates along the West Coast of South Africa (see Figure 1). The business encompasses mining, min

    Oct 5, 2011

  • AUSIMM
    A Preliminary Investigation into Electro-Strengthening of Tailings for Surface and Underground Disposal

    By Chappell B

    Backfill in the form of mine waste tailings has inherent problems associated with attaining adequate strengths upon placement. Fines are usually removed to ensure adequate drainage, which lowers the

    Jan 1, 1998

  • AUSIMM
    Zero Liquid Discharge in Coal Mining Operations

    By A Dal-Corobbo, R Zick

    The coal mining industry is now faced with new regulatory requirements that limit the discharge of chlorides into receiving streams. To meet these new regulatory standards for treated mine water, a ze

    Nov 26, 2013

  • AUSIMM
    The Competitive Challenge - Women's Contribution to Employment

    By Pratt V

    The economic, social and political environment of the mining and minerals industries is, as we all know, volatile and affected by constantly changing international forces. In addition, the outcome of

    Jan 1, 1985

  • AUSIMM
    Evolution of the modern surge-bin in mineral processing plants with highly variable feeds

    By J Lyons, S Baker, D MacHunter, D Pepper

    Mineral processing plants require a storage buffer to bridge differences in production rates between mining and processing. Where coarse ores are processed, such as coal or hard rock, this buffer may

    Aug 24, 2022

  • AUSIMM
    Lihir Gold Five Years On ù Maximising Throughput and Capital Utilisation

    During the first five years of operation, the Lihir gold mine has steadily increased plant throughput rate to over 4 Mtpa, well above the original design capacity of 2.8 Mtpa. Understanding how future

    Jan 1, 2003

  • AUSIMM
    A Phased Approach to Test Programs to Meet Feasibility Study Requirements

    By E Williams

    The role and importance of a well designed test work program during the development of an orebody is often underestimated. A test work program should be tailored to deliver very specific answers to re

    Oct 5, 2011

  • AUSIMM
    Investigation of Weathering Properties of Tailings Sand From Boliden's Aitik Copper Mine, Sweden ù A Summary of Twelve Years of Investigations

    By N Eriksson

    BolidenÆs Aitik mine, located 100 km north of the Arctic Circle in northern Sweden, is one of EuropeÆs largest copper mines. This operation produces 18 Mt of ore per year and 99 per cent of this tonna

    Jan 1, 2003