Experience Gained At The Application Of Atlas Piles In PolandBy Kazimierz Gwizdala
In recent years, in Poland the ATLAS piles have been successfully applied for some constructions near Gdansk. The piles have been used as foundations for housing and another areas of civil engineering
Jan 1, 2006
-
Production And Testing Of 600 Reinforced-Concrete Piles For The Central Bank Of IraqBy H. Meseck
The new building of the Central Bank of Iraq in Baghdad was footed in difficult underground conditions on more than 600 reinforced concrete driven piles, with cross-sectional diameters of 45 x 45 cm a
Jan 1, 1989
-
-
Kirkpatrick Street Pump Station Addition Excavation: Small Project, Big TwistBy James P. Stewart
This case history describes the engineering design and construction for the Contractor of a 35-ft-deep excavation for an 800-square-foot addition to an existing sewage pump station. The site posed une
Jan 1, 2003
-
Continuous Grouting In Embedding Of Sheet PilesBy Jouko L. Lehtonen
Sheet pile walls can be sealed watertightly using various methods. The objective of this paper is to introduce a new innovation comprising the use of continuous cement grouting during embedding. The m
Jan 1, 2006
-
Caltrans Bridge Seismic Design/Retrofit Criteria ? SynopsisBy Brian Maroney
In this paper an overview of the California Department of Transportation's (CALTRANS) bridge design criteria is presented. Special emphasis is focused upon seismic design and retrofit criteria. T
Jan 1, 1993
-
A Numerical Study On Behavior Characteristics Of Steel-Concrete Composite Drilled ShaftsBy Hyu-Soung Shin
This study is concerned with the characteristics of the behavior of steel-concrete composite drilled shafts, a material that is used for large bridge foundations, and especially for weak submerged gro
Jan 1, 2007
-
Estimation Of Settlements Of Piles In GroupBy Kazimierz Gwizdala
In the paper the method for estimation of settlement of vertically loaded piles in a group is presented. The method is generally based on the hybrid procedure with non-linear solution for single piles
Jan 1, 2002
-
Slurry Wall Design For Hong Kong StationBy Stephen T. Young
The construction of Phase 2 of Hong Kong Station, its retail podium and International Finance Centre Two, the tallest building in Hong Kong, will be completed in the middle of 2003. This paper describ
Jan 1, 2003
-
Lateral Load Testing Micropiles To Evaluate The Impact Of Threaded Joints And Casing Embedment On Short Micropiles In Shallow RockBy J. Brian Anderson
Jointed micropiles were investigated to support bridge foundations where shallow rock was present. In this application, micropiles would have some amount of unsupported length, and would be subject t
Jan 1, 2011
-
Large Diameter Steel Pipe Piles Running Under Self Weight In Soft Clay ' Predicted Vs. Observed Behavior ' Richmond San Rafael Bridge Seismic RetrofitBy A. R. Dover
The Richmond San Rafael Bridge (Figure 1) is a 4.3 mile long major toll bridge span across northern San Francisco Bay. Tutor-Saliba/Koch/Tidewater (TSKT) conducted a comprehensive seismic retrofit, wh
Jan 1, 2006
-
Permanent Canal Closures and Pumps Cofferdams – Support of Deep Excavation in Soft Ground Using the Open Cell Sheet Pile SystemBy Ryan Higbie, King Chin, Matthew Anderson, Mike Huggins, Rian Johnson, Dave Sinsheimer
"The Permanent Canal Closures and Pumps (PCCP) project is the capstone piece of New Orleans’ extensive hurricane risk-reduction system constructed following Hurricane Katrina. The project consists of
Jan 1, 2017
-
250 M Ultra Deep Milled Diaphragm Wall: The New Frontier for the Cut off Wall Depth has Been Doubled by Trevi Group TechnologyBy Maurizio Siepi, Stefano Trevisani, Pagliaccim Federico, Daniele Vanni
"Abstract: The paper describes a large innovative project completed in 2012-20123 by Trevi Group, to develop equipment capable to install ultra-deep diaphragm wall. The project highlights the capacity
Jan 1, 2014
-
Axial Pile Analyses For The New East Span Of The San Francisco-Oakland Bay BridgeBy Jacob Chacko
The east span of the San Francisco-Oakland Bay Bridge (SFOBB), which is one of the most heavily traveled bridges in the world, will be replaced due to seismic safety concerns. The majority of the new
Jan 1, 2002
-
Uplift Capacity Of Drilled Piers In Clay - SynopsisBy Braja M. Das
Laboratory model test results for the ultimate uplift capacity of square and circular foundations in saturated clay (ø=0) have been presented. The results of the present model tests for square foundat
Jan 1, 1987
-
O Street Anchored Precast Lagging And Soldier Pile Retaining WallBy John Wise
Significant movement to an existing slurry wall which serves as a retaining wall on 'O' Street in Southeast Washington, D.C. initiated the Department of Public Works for the District of Colu
Jan 1, 2003
-
The World In Steel Sheet Piling ? SynopsisBy M. Dondelinger
This paper presents a comprehensive review of steel sheet piling including internationally manufactured hot rolled sections, their history, applications, installation and driving techniques. The di
Jan 1, 2010
-
Ground Improvement by a Combination of a Mixed-In-Place (MIPTM) Lattice Grid Wall and Stone Columns to Mitigate the Risk of Liquefaction and Lateral SpreadingBy Noreen Tarac, Pablo Forgoso, Philipp Schober
A multiple use storage facility building is being developed in the Philippines on a peninsula that was reclaimed in the 1990s without any soil treatment. The subsoil now consists of loose to medium de
Sep 8, 2021
-
Tied-Down Boat Section ConstructionBy Romano J. Micciche
One of the largest scale uses of a multiple, high-strength steel bar tiedown system is described. Tiedowns were installed to resist hydrostatic uplift forces acting on a section of the Interstate High
Jan 1, 1994
-
A Novel Approach To The Performance Evaluation Of Driven Prestressed Concrete Piles And Bored Cast-In-Place PilesBy Sridhar Krishnan
This paper presents the results of a comprehensive pre-production pile testing programme for the US$ 800 million 1400MW Coal-Fired Jimah Power Plant Project in Negeri Sembilan, Malaysia. The testing p
Jan 1, 2006