Three Case Histories Comparing Impact And Vibratory Driven Pile Resistances In MarlBy Gregory J. Canivan
Three test pile programs were conducted in Charleston, South Carolina to evaluate differences in bearing resistance due to installation methods. The tested piles were installed with impact hammers and
Jan 1, 2002
-
High-Strain Dynamic Testing Of Drilled Shafts And Cast-In-Place PilesBy Garland E. Likins
High-strain dynamic testing of drilled shafts and cast-in-place piles has become routine procedure in many parts of the world today. Field testing is performed by measuring strain and acceleration rec
Jan 1, 1995
-
Friction Piles In Boston Blue Clay, Suffolk County House Of Corrections, Massachusetts ? SummaryBy Harry K. Weatherbee
The paper presents a design case study for a four-story correction facility addition in south Boston, Massachusetts, supported on friction piles driven into the Boston Blue Clay. 356 mm (14-in.) squar
Jan 1, 2003
-
Time Dependent Open-End Pipe Pile Capacity Assessment By Dynamic And Quasi-Static MethodsBy Derrick D. Dasenbrock
Three piers of a new river bridge are supported on 1.067 m diameter open-end steel pipe piles. At time of drive, and after pile re-strikes, high-strain dynamic capacity values at plan tip elevations,
Jan 1, 2006
-
Aspects of Standardization for Piles in EuropeBy Roger Frank
"Abstract After noting the importance of standardization for piles, the European system is described (execution, tests and design, etc.). Some important aspects of Eurocode 7 are outlined (like the ro
Jan 1, 2014
-
Pile Load Test Results Using The New Statnamic MethodBy Matthew Janes
Quality control procedures are increasingly important with today's higher capacity foundations and complex loading conditions. The need for a mobile, repeatable, nondestructive and economical loa
Jan 1, 1990
-
Rigid Inclusions For Soil Improvement In A 76 Building ComplexBy Walter I. Paniagua
A housing complex of 76 buildings is being constructed in the city of Morelia, in western central Mexico; the buildings are 5 levels high, with a shallow concrete slab foundation. Soil conditions incl
Jan 1, 2008
-
Presentation #6 - Rapid Load Testing: A New Choice For Pile TestingBy Michael D. Justason
...a global perspective... In March of 2000, the Japanese Geotechnical Society added "Rapid Load Testing" to their national standard for pile testing. In the year 2000. it is estimated that th
Jan 1, 2001
-
Case Histories Of Geo-Column? Foundations - SynopsisBy Osamu Taki
This paper presents the system, the strength of column, the design concept, and the applications with four case histories from the past project as the general aspect of Geo-Column (trade mark of singl
Jan 1, 2000
-
Machine Foundation RepairBy Scott D. Thomson
The client for this project specializes in the use of state-of-the-art technology to fabricate and assemble composites and metal-bonded structures for commercial and military aircraft programs. One of
Jan 1, 2003
-
Bearing Capacity Of Long Piles Driven Into Soft Soil ? SynopsisBy F. Z. Suo
Baoahan Iron and Steel Complex is situated at lower beaches of the Yangtze River. The subsoils 50~70 M below the surface is a deposite of Yangtze River delta, consisting mainly of weak silty clay and
Jan 1, 2010
-
Use Of Helical Piles Set Into Soft Rock For 1500-Ton Screw Press FoundationBy David C. Kraft
A major manufacturer and user of machine tools had the need to install a screw press machine at its plant site with the following design load requirements: (1) Vertical Compression Live Load = 2000 ki
Jan 1, 2003
-
Tanana River Bulkhead Expansion, Flexibility In Construction; Key To Arctic Dock ConstructionBy Roy Peratrovich
An innovative cost-saving design for a 1,100 ft bulkhead on the Tanana River at Nenana in central Alaska won Alaska Construction & Oil magazine's Construction Achievement Award. The designers uti
Jan 1, 1985
-
Drilled Shaft Difficulties and a Micropile SolutionBy Jeff Jackson, Paul Axtell, David Graham
The Montana Department of Transportation recently awarded a contract to construct a replacement bridge across the Clark Fork River in Heron, MT. Both abutments and both intermediate bridge bents were
Jan 1, 2018
-
Developing Effective Specifications For Tremie-Concrete Placement In Drilled ShaftsBy Giuliana A. Zelada-Tumialan
Reduced workability and flowability of the concrete through the tremie tubes and drilled shaft reinforcement have been identified as the main causes of tremie-concrete drilled shaft concrete defects.
Jan 1, 2009
-
Foundation Design And Construction In Variable RockBy Joel Moskowitz
A new office complex is being constructed within 25m of the Hudson River in New Jersey. The project, about 140 m by 100 m, will include 4 basements under the entire footprint. The perimeter was to be
Jan 1, 2002
-
Analysis Of Static And Dynamic Horizontal Load Tests On Steel Pipe PilesBy Pastsakom Kitiyodom
In order to estimate the deformation and load distribution of a single pile subjected to dynamic horizontal load as well as vertical load, a simplified method of three-dimensional numerical analysis,
Jan 1, 2006
-
Deep Bored Piling in Soft Soil and High Lateral LoadsBy W. Sondermann
"AbstractThe construction of a distribution centre of minerals for a global mining and resources cooperation demanded the control of deformations and displacement of the stack reclaimer facilities on
Jan 1, 2014
-
The Determination Of The Property Index Of Stabilizing Agent And Computer Simulation For The Optimum Mix In Deep Foundation ConstructionBy Li Huimin
In this paper the step of determining the property index and the program of mixture ratio design of stabilizing agent in deep foundation construction are presented. According to the principle of compu
Jan 1, 1991
-
Dynamic Horizontal Load Tests On Steel Pipe Piles Having Different Sizes In The Same Construction Site And Their AnalysesBy Eiji Kojima
In this research, dynamic and static load tests were performed on permanent foundation piles which had a pile length of 30 m, 800 mm in outer diameter and 15 mm in wall thickness. In this site the dyn
Jan 1, 2006