Underpinning Atlanta International Airport Concourse E for APM Tunnel ExtensionBy Clinton O. Rex, Adam S. Hurley, W. Morgan NeSmith
"Hartsfield-Jackson Atlanta International Airport underwent a $1.2 billion dollar expansion project centered on the construction of the new Maynard H. Jackson International Terminal. Passenger access
Jan 1, 2017
-
Design Of An Unbraced Elliptical Slurry Wall Cofferdam For Deep Pump Station ConstructionBy Gordon Chen
As part of a value engineering envisioned by East Coast Slurry, Weidlinger Associates, Inc. designed a unique elliptical slurry wall cofferdam for construction of the 65 ft. deep MWRA North Dorchester
Jan 1, 2010
-
Design Solutions for Seepage End-Around-Effects at Cutoff Wall Depth TransitionsBy Michael Hughes, Selva Selvamohan, Ray Costa
"Cutoff walls are commonly used to mitigate underseepage problems for levee remediation projects. At abrupt changes in seepage cutoff wall depths there is a potential for water to flow around the back
Jan 1, 2015
-
Data Drives Herbert Hoover Dike (Hhd) Rehabilitation EffortsBy Michael Arnold, Jignyash Manyam, Yoav Rappaport
The USACE required construction of over 13 miles of cutoff wall at an average depth of 65 feet for the Herbert Hoover Dike (HHD). To meet project requirements, to provide quality control and make soun
Oct 1, 2022
-
Diplomacy And Innovation: Octakong And The Hong Kong-Zhuhai-Macau Bridge ProjectBy David White
When finished (projected completion in 2016) the Hong Kong-Zhuhai-Macau Bridge Project will comprise three cable-stayed span bridges and a 4.15 mile immersed tube tunnel - linking Hong Kong to Macau a
-
Diplomacy and Innovation: Octakong and the Hong Kong-Zhuhai-Macau Bridge ProjectBy David White
"When finished (projected completion in 2016) the Hong Kong-Zhuhai-Macau Bridge Project will comprise three cable-stayed span bridges and a 4.15 mile immersed tube tunnel - linking Hong Kong to Macau
Jan 1, 2017
-
Grouting of an Artesian Zone in Advance of Powerhouse Excavation for the Red Rock Hydroelectric ProjectBy Dewey W. Geary, Rachael V. Bisnett, R. Michael Bivens, Thomas G. Andrews
"The powerhouse for the Red Rock Hydroelectric Project is being constructed at the toe of the existing U.S. Army Corps of Engineers’ Red Rock Dam immediately adjacent to the existing stilling basin re
Jan 1, 2016
-
Hammer-Grout Piles At The Bronx-Whitestone BridgeBy Ameir Altaee
Unconventional means and methods were utilized to install over 650 contractor-designed micro-piles for the replacement of the Bronx approach to the Bronx-Whitestone Bridge in New York City. The metho
Jan 1, 2010
-
Resonance Pile Driving with Zero Ground VibrationBy Mark Johnson, Mathew Janes
"The Resonator RD 260 Resonant Pile Driver delivers ground disturbance free, high production pile driving. The Resonator has recently been used on numerous production pile driving sites in the Netherl
Jan 1, 1900
-
Seismic Design Of Micropile Foundation SystemsBy Leo Panian
Over the last decade, drilled and post-grouted micropile foundations have come to be increasingly relied upon for resisting seismic loads in building foundations on the West Coast. Micropiles have bee
Jan 1, 2010
-
Noise Attenuation and Reduced Risk Associated With New Double- Walled Pile TechnologyBy Julie H. N. Hampden, Per G. Reinhall
"Executive summary: Impact pile driving of steel piles is a common construction practice in freshwater and marine environments for the building of structures and foundations. This practice produces ex
Jan 1, 2017
-
A New Low-Cost Bi-Directional Load Test Technique for Drilled ShaftsBy Sherif Elfass, Gary Norris
Bi-directional load testing of drilled shafts has been widely adopted as a means to evaluate their load carrying capacity. However, in order to reach failure, most of these tests are carried out on s
Sep 8, 2021
-
Construction Of The Drilled Shaft Foundations For The Huey Long Mississippi River Bridge, New OrleansBy Dan A. Brown
The foundations at the Huey P. Long Bridge in New Orleans presented special challenges for construction due to the requirements for very deep drilled shafts in the Mississippi River beneath the existi
Jan 1, 2010
-
MnDOT's I35W Stormwater Storage Facility - Flooding Resolution in Challenging Ground Using a Series of Six Diaphragm Wall CellsBy Thomas Pullen, Gregory Spicer, Joe Welna, Lola Moussey
During the past several decades, a segment of Interstate 35W (I-35W) at 42nd Street, located in Minneapolis, Minnesota, has experienced flooding during intense storm events. Flooding is caused by a co
Oct 7, 2024
-
Sustainability and Consideration of the Re-Use of Foundations for the Hurricane Deck BridgeBy Timothy C. Siegel, Paul J. Axtell
The Missouri Department of Transportation (MoDOT) recently replaced the Hurricane Deck Bridge that carries Highway 5 traffic across the Osage Arm of the Lake of the Ozarks in Camden County, Missouri.
Jan 1, 2017
-
Analysis And Performance Of Sheet Pile Cofferdam Under Demolition Blast LoadsBy Michael Oakland
This paper will discuss the design analysis of sheet pile cofferdams for static and dynamic blast loads. Following construction of the new Willis Avenue Bridge across the East River between Brooklyn
-
Analysis and Performance of Sheet Pile Cofferdam under Demolition Blast LoadsBy John Mould, Gordon Chen, Michael Oakland, William McElwee
"This paper will discuss the design analysis of sheet pile cofferdams for static and dynamic blast loads. Following construction of the new Willis Avenue Bridge across the East River between Brooklyn
Jan 1, 2017
-
Rigid Inclusion Quality Control and Performance Verification Using Drilling Parameters: A Streamlined ApproachBy Jesus Gomez, Carlos Englert, Amanda Mallon, Mary Nodine
Rigid inclusions are a ground improvement technique that provides soil reinforcement and settlement mitigation using drilled displacement elements. Rigid inclusion installation typically uses a Monito
Oct 7, 2024
-
Friction Loss in Tieback Anchors used for Landslide StabilizationBy John P. Turner, Benjamin J. Turner
"Tieback anchors are now used routinely for landslide stabilization in the USA and abroad. It is generally understood by design engineers that friction loss over the unbonded length of a tieback ancho
Jan 1, 2017
-
Innovative Alternate Underpinning Solution for Historic Structure in Boston SuburbBy Eric P. Bregman, Justin Zarrella, Ryan M. Coulson, Connor Johnson
Within a prominent Boston, MA suburb are a pair of historic stone and mortar structures built in the late 1800’s. Both the Main House and Carriage House have been maintained and occupied throughout th