Approach Wall Foundations Olmsted Locks And Dam Project ? SummaryBy Jeffrey A. Schaefer
The Olmsted Locks and Dam project is located on the Ohio River approximately 16.5 miles upstream of its confluence with the Mississippi River. It consists of twin 1200 ft. locks with floating and fixe
Jan 1, 2001
-
Load Testing Of Deep Foundations Using The Osterberg Load CellBy David E. Thompson
This paper describes the full-scale field load testing of three deep foundation units using the Osterberg Load Cell. The load tests were completed on three separate projects, two in Massachusetts and
Jan 1, 1989
-
Modification of Best-Fit Interpretation Method for Ultimate Capacity of Screw PileBy Adnan A. Malik, Tadashi Maejima, Jiro Kuwano
"ABSTRACTTheoretical approach to estimate the ultimate pile capacity gives a rough idea at the initial stage of design that later on strengthen by the execution of static pile load test at site. The s
Jan 1, 2014
-
The Spadina Pier Cofferdam - Design, Installation & PerformanceBy Jan A. Nilsen
This paper describes a key element in the construction of a major project undertaken by Harbourfront Corporation in its efforts to rejuvenate the central Toronto waterfront. The Spadina Pier forms one
Jan 1, 1987
-
Site Management Towards Pile Execution At Qurashiya BridgeBy Emad W. Shublaq
Contractual site plans are implemented for executing pile foundations (5 x 5) at segmental concrete bridge. Project schedule demands have forced the contractor to find out the most economical procedur
Jan 1, 1992
-
Underpinning A Crane FoundationBy Donald R. McMahon
This paper presents a unique case history that documents the use of a braced secant pile wall to underpin a heavily loaded footing inside of a manufacturing plant. Construction of a pit for a new man
Jan 1, 2006
-
Special Foundation Technique For The Intersection Of Two Canals Near Magdeburg, Germany - Summary:By Wolfgang G. Brunner
The closing of the gap in the European waterway- net is one of the big and challenging traffic projects following the German reunification. The water canals in the North German plain connect the Rhine
Jan 1, 2000
-
SFMOMA Expansion – Multiple Uses of Ground Improvement – A Case StudyBy Scott A. Walker, Frank L. Rollo
"The San Francisco Museum of Modern Art (SFMOMA) in downtown metropolitan San Francisco, California, is supported on a mat foundation. Although the mat foundation of the original museum was designed t
Jan 1, 2014
-
The Heritage of Swedish Foundation EngineeringBy Stefan Aronsson, K. Rainer Massarsch
"ABSTRACT The geology of Sweden is characterized by the most recent glacial period with deposition of very soft clays and loose sand. Due to these difficult geotechnical conditions, new, innovative fo
Jan 1, 2014
-
-
Laboratory Validation Of In-Situ Tests - 1. IntroductionThis paper summarizes seven years of Italian experience with the use of large calibration chambers for the calibration, under closely controlled stress and strain conditions, of some in situ testing
Jan 1, 1987
-
Repurposing Existing Features for a New Support of Excavation SystemBy Andrew Moran
In 2021, the University of Pittsburgh began construction of a new recreation and wellness center for students and faculty in the heart of its main campus in Pittsburgh. The design and plans for the ce
Jun 1, 2024
-
Single-Head Large Diameter Hammer Drill For Bored Piling Actualizes Large Diameter Rock Drilling And Deep Underwater Drilling Operation - SynopsisBy J. Nakayama
Down-the-hole hammer is commonly recognized as the most powerful drilling equipment for weathered to fresh rock formation including boulders. However, its drilling diameter is restricted by reasons of
Jan 1, 1996
-
Conference Papers - Conference Papers: Session 1 - Construction Of A Deep Basement On A Sloping Site In Glasgow: The Aurora ProjectBy H. Boghosian
This paper presents the design and construction of a deep basement in a steeply sloping site in glacial till in Glasgow city centre. Existing foundations, adjacent structures and services, in tandem w
Jan 1, 2006
-
Influence of Presence of Overlaying Sand on Rock Socket Length of Bored PileBy Priyadharshini M. R., Premalatha K
"Abstract With the development in the construction of heavily loaded structures, the necessity of pile foundations has increased. For the transfer of heavy loads, it is mandatory that the piles need t
Jan 1, 2014
-
Deep Mixing Method: A Global PerspectiveBy Donald A. Bruce
Various types of contemporary Deep Mixing Method (DMM) techniques have been used in the United States since 1986. Such techniques owe their origins to Japanese and Scandinavian developments, which beg
Jan 1, 1998
-
Execution And Evaluation Of High Capacity Caisson Load Tests In Glacial DepositsBy Franklin M. Grynkewicz
As part of the Boston Harbor clean up project, the new 1,000 mgd Deer Island Sewerage treatment plant includes ten 240 feet high egg-shaped "residuals" tanks. Contract documents called for these struc
Jan 1, 1992
-
The Little Lake Harris Bridge Settlement Restoration Project: Lessons LearnedBy Amr Sallam, David Thompson, Moataz Hassan
"The Little Lake Harris (LLH) Bridge was constructed in 1951 to replace the eastwest County Road 48 Bridge connecting the towns of Howey-in-the-Hills and Astatula in Lake County, Florida, United State
Jan 1, 2015
-
Session 21 "Grouting in Karst"By Jim Henry
I would say mainly the cost. I showed only 3 cases. One of them was the one that Allen just described and there were two other cases. In those cases it was fairly easy to develop a solution using limi
Feb 10, 2003
-
Unusual Solutions To Difficult Earth Retention And Underpinning Projects ? SummaryBy Larry Rayburn
Design of cost effective engineered solutions to complex problems requires the team efforts of the owner, the designer and the specialty construction contractor. The basic ingredients of success requi
Jan 1, 1991