Tenneco's Green River project : Foresight and patience pay off

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 3
- File Size:
- 603 KB
- Publication Date:
- Jan 10, 1985
Abstract
Introduction In 1967, Tenneco acquired Kern County Land Co. The primary reason for the acquisition was to obtain Kern's agricultural, manufacturing, and oil interests. Included in the Kern portfolio were the core of Tenneco's present sodium leases in Sweetwater County, WY. This lease base has been ex¬panded and now consists of 62 km2 (24 sq miles). Beneath this property lies more than 500 Mt (550 million st) of economic trona ore. Following the Kern acquisition, Tenneco continued exploration and feasibility studies concerning the trona leases. The effort was accelerated in 1976. Tenneco was attracted to trona because of the favorable lease position it held, the growth rate of the Wyoming industry during the 1960s and 1970s, and the prospects for a long-term, stable business enterprise. The reserve picture was certainly attractive to a company long accustomed to the never-ending struggle to replace oil and gas reserves. In 1978, Wyoming was a boom area that had experienced rapid growth for a number of years. Unemployment was very low and vacant housing nonexistent. The prospects for soda ash were somewhat different in the 1970s than now. But it was recognized even then that a new producer would have a challenging task to compete in this business. Tenneco knew the capital burden required to build a grassroots facility during inflationary time, would have to be offset elsewhere Since labor and energy are the dominant direct costs in mining trona and producing soda ash these factors have always received a great deal of attention. Contracting and permits Environmental monitoring on the site began in late 1977. With the already mentioned considerations in mind, engineering began by mid-1978. Brown & Root Inc. was selected as the general contractor for the project. S. A. Scott & Co. was the engineering subcontractor for the mine shafts, hoists, ventilation system, and miscellaneous mine facilities. Frontier-Kemper was awarded the contract for sinking the two mine shafts. Acquisition of numerous federal, state, and local permits occupied all of 1978 and 1979. The Wyoming Industrial Siting Permit, which addresses socioeconomic issues, drew the most public interest. Siting issues were all satisfactorily resolved by negotiating reasonable stipulations with various local governmental units, school districts, and the like. Site location The Green River project location is not truly remote. It is located within 5 km (3 miles) of Interstate 80 and only about 32 km (20 miles) west of the city of Green River. Nevertheless, a substantial investment had to be made in communication and utility links to the site. These included: • A 14-km (8.5-mile) rail spur connecting with the Union Pacific Railroad at Bryan, WY. This spur has four bridge structures including one crossing Interstate 80. Most soda ash is shipped by rail, and coal is received over this line as well. • A paved 5-km (3-mile) roadway connecting to Interstate 80. • A powerline extension of about 27 km (16.5 miles), along with two new substations. • A 24-km (15-mile) waterline connecting the plant to a pump station on the Green River. The site is located on gently sloping terrain at an elevation of about 2.1 km (6800 ft). Ground conditions are good for construction. Weathered bedrock lies near the surface in most places. Geology The general geology of the Green River Basin has been well described previously. Tenneco's ore is in several superimposed evaporate beds. But the bulk of it is present in Bed 17, located about 457 m
Citation
APA:
(1985) Tenneco's Green River project : Foresight and patience pay offMLA: Tenneco's Green River project : Foresight and patience pay off. Society for Mining, Metallurgy & Exploration, 1985.